Chapter 4: Verifying and Operating • 61 V erifying the Joystick See the PCS or Nucleus user’s guide for details on using the joystick. You can move the stage with the joystick. Try manipulating the joystick while you wat…

60
• Summit 11K/12K Probe Station User’s Guide
Point and click the mouse in the same way you use the mouse with other
Windows applications.
To execute the tests
• Click a test button to run a single test only.
--OR--
• Click the All button to run all tests sequentially.
--OR--
• Choose a test from the Test menu.
--OR--
• Choose All from the test menu to run all tests sequentially.
Some tests, such as Motors and Light, require your observation and input for a
pass or fail decision.
To view a test’s dialog box without running the test
Choose Virtual mode from the Option menu, then choose the test.
NOTE
You must turn Virtual mode off before running a test on the hardware.
To clear the results of tests
Choose Clear status from the File menu.
To run tests repeatedly
Cascade recommends that you occasionally run all the tests ten times in a row.
Click the Exercise button to run the tests repeatedly. Each exercise cycle takes
about one minute to complete.
• Choose Exercise during installation.
• Choose Exercise if you suspect the probe station has an intermittent problem.
To exit verify
• Choose Exit from the File menu to exit Verify.
--OR--
• Click the Close button.
To get more information on verify software
Click the Help button or open the Help menu.

Chapter 4: Verifying and Operating •
61
Verifying the Joystick
See the PCS or
Nucleus user’s
guide for details on
using the joystick.
You can move the stage with the joystick. Try manipulating the joystick while you
watch the stage movement through the microscope.
Two slide switches on the joystick base regulate its tendency to return to center
when released. You can adjust the switches so that:
• The joystick centers and all stage movement stops when you release the
joystick.
--OR--
• The joystick remains where you release it and the stage continues to move in
the same direction until either you stop it or it reaches the limit switches.
Testing procedure
1. Click START | Settings | Control Panel.
2. In the Control Panel group, double-click the Joystick icon.
3. Click the “Test” button.
4. Move the joystick and watch the on-screen crosshairs move the same relative
direction and distance.
5. Press the Turbo buttons (located on top of the joystick and the left of the
joystick base) and watch Button 1 depress on-screen.
6. Press the Accept button on the right of the joystick base and watch Button 2
depress on-screen.
The Joystick test passes when the joystick and crosshairs move together and when
the joystick and on-screen buttons work together.
Testing the Thermal Chuck
(Thermal Stations Only)
FIRST STEP
Purge the MicroChamber with dry air
1. Close and lock the access door to the MicroChamber.
2. Lower the microscope to the down position, so the microscope objective seal
is flush to the TopHat (for Mitutoyo and A-Zoom microscopes only).
3. Make sure that the TopHat is sealed against the MicroChamber.
4. Make sure compressed-air is connected and flowing to the air dryer.
5. Power up the air dryer.
6. Adjust the air-flow control (counterclockwise increases air flow) to purge the
MicroChamber to at least seven standard cubic feet per minute (SCFM).
7. Allow the dry air to purge for at least 30 minutes.

62
• Summit 11K/12K Probe Station User’s Guide
N
OTE
If the system has not been purged for several days, you should purge the system
for 30 minutes. For subsequent purges, 15 minutes should be sufficient.
After the initial purge you can reduce the purge flow rate to three SCFM. Chuck
temperature transitions occur faster at lower purge rates.
Never operate the system with a purge flow rate less than three SCFM
at
temperatures below 41°C.
For temperatures above 41°C, use a purge flow rate of two SCFM to minimize
thermal coupling between the chuck and the probes and cables.
SECOND STEP
With the Temptronic controller, fill the coolant reservoir
1. Turn on the Temptronic controller.
2. Fill the coolant reservoir. See also, the Temptronic manual.
3. Power up the station.
4. Set T1 and T2 on the Temptronic controller to the desired temperatures
(between -55 and +200°C). See the section “Local Operation” in the
Temptronic ThermoChuck Operator’s Manual for how to set temperatures.
5. Wait until the Temptronic controller verifies that the specified temperatures
are reached.
6. Inspect the coolant lines and fittings for coolant leaks. If there are no leaks,
slide the insulating covers over the fittings.
7. Check for frost on the chuck. Check at different temperatures to ensure that
frost is not accumulating.
8. If frost forms, see Troubleshooting.
Air Dryer Settings
See air dryer
documentation.
When you first purge the MicroChamber at the end of installation, or when you
haven't used it for several days, set the flow rate at 7 SCFM for 30 minutes to
thoroughly dry the MicroChamber. After the initial purge, you can reduce the
purge time to 15 minutes after each time you open and close the MicroChamber.
After purging, you can set the operating temperature. Set the flow rate at 3 SCFM
for temperatures below 41°C. For temperatures above 41°C, set the flow rate to 2
SCFM.
Handling Wafers with the MicroChamber
DANGER
Chuck bias voltages can be lethal; chuck temperature extremes can cause serious
injury. Before opening the MicroChamber access door, ensure that voltage is not
applied to the chuck, and the chuck is not at a temperature extreme.