N7201A617E00_0317 - 第346页
NPM-W 2 EJM7DE-MB-13M-00 STEP Item Action Changes in machine condition and calibrations to be performed Time required [Min] Relocation, change in floor level Replacement of head 1) STEP1 Head camera XY origin Camera an…

NPM-W2 EJM7DE-MB-13M-00
13-1-1-2
Calibration

NPM-W2 EJM7DE-MB-13M-00
STEP Item Action
Changes in machine condition
and calibrations to be performed
Time
required
[Min]
Relocation,
change in
floor level
Replacement
of head
1)
STEP1
Head camera XY origin
Camera angle
5
XY origin camera scale
5
Plane correction XY Plane correction XY
30
STEP2
Plane correction Z
Height measurement
5)
5
Plane correction Z
5)
20
Dummy dispensing
height
()()
5
Width adjustment Width adjustment
10
Placement
position/Conveyor
Height measurement
5
PCB stop position
5
Height sensor
(option)
Height measurement
()()
10
Placement load
(3-nozzle head)
Placement load
measurement F1 and F2
15
STEP3
Multi-recognition camera
Head
origin
5
Camera offset
10
Jig station
(per head)
Scan position
4) 5)
4)
40
2)
Nozzle changer height
4) 5)
Head camera lighting
Multi-recognition camera
lighting
4) 5)
Head offset
4) 5)
4)
Dispensing head (option)
Head
origin
()()
5
Head offset
()()
5
White balance (option: 2D
inspection head)
White balance adjustment
5
Get target values of
calibrated PCB
5
Camera offset (option:2D
inspection head)
-
()
5
Image quality correction
(option: 2D inspection head)
-
()
30
Inspection plane correction
(option: 2D inspection head)
-
()
5
STEP4
Pickup position Pickup position
10
Tray (option)
Pickup height
()
10
Pickup position 1
()
Pickup position 2
()
Transfer Height measurement
()()
10
■Calibration item and action
Over-
view
Calibration item and
action
13-1-2-1
Maintenance
13-1-2

NPM-W2 EJM7DE-MB-13M-00
STEP Item Action
Changes in machine condition
and calibrations to be performed
Time
required
[Min]
Relocation,
change in
floor level
Replacement
of head
1)
Accuracy
verification
Placement accuracy, Reflection
4) 5)
4)
30
Placement accuracy, Verification
4) 5)
4)
30
2D inspection head, Reflection (option)
()
15
2Dinspection head, Verification (option)
()
15
Dispensing head accuracy, Reflection (option)
()()
15
Dispensing head accuracy, Verification (option)
()()
15
13-1-2-2
:Perform ():Perform only on a machine with any optional unit
*1) Perform calibration only on the table of which the unit has been replaced.
*2) Time required for the light weight 16-nozzle head. 12-, 8-, and 3-nozzle heads require 35, 30, and 20
minutes, respectively.
*3) Calibration is also required when APC option is purchased and a head is installed.
*4) It is not carried out for the dispensing head.
*5) It is not carried out for the 2D inspection head.
Calibration