NPM- TT2 EJM1EE-MB-13 M-02 STEP Item Action Changes in machine condition and calibrations to be performed Time required [Min] Relocation, change in floor level Replacement of head *1) STEP1 Head camera XY origin Camera a…

NPM-TT2 EJM1EE-MB-13M-02
Over-
view
Maintenance
13-1-1
Calibration
performance
To maximize the machine’s capability, you need to adjust parameters installed on the machine to the site
environment. This task is called calibration.
This chapter describes the calibration method.
■Do this task if any of the following events should occur;
●Relocation of the machine.
●Replacement of unit(s).
●Floor level change.
■Observe the following conditions as you perform the task.
●Turn ON the main power switch of the machine at least one hour before you start the task.
●Do not warm up the machine before you start the task.
●Wait for over an hour to start the task, immediately after the machine stops production or warm-up
operation.
13-1-1

NPM-TT2 EJM1EE-MB-13M-02
STEP Item Action
Changes in machine condition and
calibrations to be performed
Time
required
[Min]
Relocation,
change in
floor level
Replacement
of head
*1)
STEP1
Head camera XY
origin
Camera angle
5
XY origin camera
scale
5
Plane calibration XY Plane calibration XY
30
STEP2
Head / Plane
calibration Z
Height measurement
5
Plane calibration Z
20
Width adjustment Width adjustment
10
Placement
position/Conveyor
Height measurement
5
PCB stop position
5
Height sensor
(option)
PCB height
measurement
()()
10
Placement load
(3-nozzle head)
Placement load
measurement F1 and
F2
15
STEP3
Multi-recognition
camera
Head
origin
5
Camera offset
10
Jig station
(per head)
Scan position
30
*2)
Nozzle changer
height
Head camera lighting
Multi-recognition
camera lighting
Head offset
Split recognition
(3-nozzle head)
Camera offset
5
STEP4
Pickup position Pickup position
10
Tray
Pickup height
()
10
Pickup position 1
()
Pickup position 2
()
Transfer Height measurement
()()
10
Accuracy
verification
Placement accuracy, Reflection
30
Placement accuracy, Verification
30
:Perform ():Perform only on a machine with any optional unit
*1)Perform calibration only on the table of which the unit has been installed or replaced.
*2)Time required for the 8-nozzle. 3-nozzles require 20 minutes.
■Calibration item and action
Over-
view
Calibration item and
action
13-1-2
Maintenance
13-1-2
Calibration

NPM-TT2 EJM1EE-MB-13M-02
Over-
view
Jigs used for
calibration
■STEP 2
Menu Jig
Head camera XY
origin
Plane calibration XY
■STEP 1
13-1-3-1
NOTICE
Maintenance
13-1-3
Menu Jig
Head / Plane
calibration Z
Placement position /
Conveyor
8-nozzle head
:230C
3-nozzle head
:1002 nozzle
Width adjustment
Placement load
(3-nozzle head)
Height sensor
(option)
Placement load
measurement jig
(N610084605AB)
Load cell meter
(N610093887AD)
1003 nozzle
(KXFX037UA00)
Height sensor jig
(N610122649AA)
Plane calibration jig
(N210147296AC)
Plane calibration jig
(N210141055AB)
X 2 plates
X 1
plate
PC size conveyor
M size conveyor
Common to NPM-W/W2,
AM100
Common to NPM-
D/D2/D3/TT
230C nozzle and 1002 nozzle are not included with the calibration jig (option).