Calibration HLGB-10304-01 Auto Calibration (Recognition of relationship betw een PWB coordinate and mechanism coordinat e) SHEET 3/7 3. Loosen cap screws ( CP4x6) to remove the pin marker . 4. Loosen cap screws (2 -CP4x1…

100%1 / 712
Calibration
HLGB-10304-01
Auto Calibration (Recognition of
relationship between PWB coordinate and
mechanism coordinate)
SHEET
2/7
3 Shut off the power of the unit.
Do not shut down the power from the start
menu of Windows
®
.
1. Press the power off switch.
Shutting down of the system starts and the power
is automatically shut off.
2. Turn off the main breaker.
The power receiving lamp on the power panel
lights off.
4 Prepare to install the ball point jig.
1. Remove the Lower cover and the
shooter from the front and rear side of
the unit.
Tile the lower cover slightly toward you and pull
the fan cable to remove the lower panel.
2. Remove all the nozzle cartridges from
the rear side of the unit.
Lower cover
Shooter
Nozzle cartridges
Main breaker
Power off switch
Calibration
HLGB-10304-01
Auto Calibration (Recognition of
relationship between PWB coordinate and
mechanism coordinate)
SHEET
3/7
3. Loosen cap screws (CP4x6) to remove
the pin marker.
4. Loosen cap screws (2-CP4x10) to
remove the movable rail stopper.
5. Unscrew the cap screw (12-CP4x10) to
remove the PWB holder installed on
the conveyer.
5 Turn on power for the unit to return to home.
1. Turn OFF the main breaker.
2. Press the power on switch.
The unit starts.
3. Press the [ORG] button on the
operation panel with the HI screen
being displayed.
The unit return to origin.
6 Return the CV-axis to the original position.
1. Click in an order of MANUAL menu
PWB TRANSPORT tab Conv. Wid.
Adj. button.
Conv. Adj. screen is displayed.
Movable rail
stopper
Pin maker
PWB holder
Cap screw
Calibration
HLGB-10304-01
Auto Calibration (Recognition of
relationship between PWB coordinate and
mechanism coordinate)
SHEET
4/7
2. Press the [ORG] button on the
operation panel with the Conv. Adj.
screen being displayed.
Conveyor return to origin.
3. Click the Return button to close the
Conv. Adj. screen.
7 Move the head clear of the work area.
1. Click in an order of AXIS MOTION
tabXY button.
XY Axis screen is displayed.
2. Operate the XY axis screen to move
the head to a position where working
can be easily performed.
Absolutely move the head to a position of X=100,
Y=300, then the subsequent working easily
becomes performed.
8 Install the ball point jig.
1. Clean surface of the ball point jig and
all of holes with waste cloth.
2. Position the ball point jig on the
conveyor rail referring to the pin
positions.
Ball point jig