WaferTransportSolutionManual - 第94页

INSTALLATION EQUIPMENT INSTALLATION 3.18 Wafer Transport Solutio n Chapter Issue 1 Aug 11 NOTE If the printer has product file s created previously , the user should check that the product parameters are su itable for th…

100%1 / 116
INSTALLATION
EQUIPMENT INSTALLATION
Chapter Issue 1 Aug 11 Wafer Transport Solution 3.17
Power Up 1. Power up the printer.
2. Select Maintenance.
3. Select Diagnostics.
NOTE
The printer’s software automatically checks for the Wafer Transport Solution
hardware via Node 17. If the software fails to recognise the option, users
may set up products but the printer fails to run. To avoid this, the following
section of this procedure is used to check that the software has recognised
that the hardware is fitted.
Hardware
Recognised Check
4. Select Rail System.
5. Select Run Diagnost..
6. Check that the following diagnostic elements are included in the list:
Toggle Heavy Rail Drop
Set Decel Offset Window Calibration
NOTE
If the above parameters are not listed, the software has not recognised the
hardware is fitted.
7. If the elements are listed, go to Step 11, else:
8. Check that the correct software is loaded for the application.
9. Power down the printer.
10. Referring to drawing 200483 Circuit Diagram -Thin Wafer Handling (located
at the end of this manual); check the connectors and motor of the Heavy
Pallet Servo Node 17.
11. Repeat Steps 1 to 5 above to confirm that the software recognises the
hardware. If the elements are still not listed contact DEK Customer Support
Group for assistance.
12. Exit the diagnostics page. The printer initialises.
Load a Product File 13. From the Ready page select Setup Product.
14. Select Load Product.
15. Select a suitable production product from the list and load the product.
INSTALLATION
EQUIPMENT INSTALLATION
3.18 Wafer Transport Solution Chapter Issue 1 Aug 11
NOTE
If the printer has product files created previously, the user should check that
the product parameters are suitable for this application (physical dimensions
may be unsuitable). The existing product parameters can be edited if
necessary.
Level the Printer 16. Select Tooling.
17. Select Setup Tooling.
18. Select Transport Height.
19. Select Toggle Board Clamps. This step raises the beams up.
20. Level the printer (printer transport heights are to match the downline/upline
systems’ transport height). Full levelling instructions are given in the printer
installation manual.
Level the CHAD/NUTEK Conveyor
WARNING
HEAVY OBJECT. EXTREME CAUTION SHOULD BE EXERCISED WHEN
MANUALLY HANDLING HEAVY ITEMS INTO OR OUT OF THE MACHINE.
21. Adjust the conveyor rail width to accommodate the pallet.
Figure 3-7 NUTEK Linking Conveyor Rail Width Adjusters
22. The printer is in position and level; align the conveyor system to it (adjust
the four feet a little at a time).
23. If the printer is located to the right of the conveyor, adjust the left side of the
conveyor to bring its transport rails level with the printer transport rails.
24. Level the conveyor to the correct height, matching the printer at transport
height.
25. Manually load a pallet onto the conveyor transport rails.
26. Move the pallet, by hand, into and out of the printer (half and half), check
that it does not bind, lift, or drop when moving on the rail systems of each
machine. Make adjustments to the line levelness and alignment as required.
Rail Width Adjuster Rail Width Adjuster
INSTALLATION
EQUIPMENT INSTALLATION
Chapter Issue 1 Aug 11 Wafer Transport Solution 3.19
27. Repeat the steps for levelling and apply them to the other printer.
28. Remove the pallet.
Pneumatic
Connections
Three vacuum connections from the pallet transfer station are available in its
drag chain. On the pallet, they connect to the two stacked elbow connectors
(pin and wafer) and the single delta ‘tee’ connector (shim). See detail in the
Precision Wafer Pallet Chapter. The connections are push fit, they make the
connections to the underside of the pallet.
Figure 3-8 Simplified View of the Vacuum System
Flow Restrictors The DEK printer flow restrictors need to be balanced to ensure that the pallet
does not ‘drop’ into place in the print area.
1. Open the printhead front cover.
2. Load a pallet into the centre section of the printer.
3. Close the printhead front cover.
4. Press the System button.
5. Select Maintenance.
6. Select Diagnostics.
7. Select Rail System.
8. Select Select Module.
9. Using Decr. or Incr. select Cycle Board Clamp.
10. Select Run Diagnost..
11. From the side of the printer, observe the pallet lift/drop section of the cycle.
The pallet should be placed in a controlled manner onto the support blocks.
If adjustment is not required exit the diagnostic and remove the pallet.
Pallet and
Lift Pin
Elbows
Shim Vacuum
Delta ‘Tee’
Vacuum Switch
Vacuum Control
(See Transfer Station
documentation for details)
Drag Chain
Shim Vacuum
(non-switched)
Pallet & Shim
Pallet & Lift Pin Vacuum
(switched)
Underside of Pallet