TR7600 SIII_Series_Installation_en_v_2_0_2 - 第10页
在线预览 TR7600 SIII_Series_Installation_en_v_2_0_2 PDF 文档。

Test Research, Inc.
iii TR7600 SIII Series User Guide – Installation
Figure 40: The Connection of Repair Station ................................................................. 21
Figure 41: Loader Socket Position .................................................................................. 22
Figure 42: Loader and Unloader Socket Position ........................................................... 22
Figure 43: Loader and Unloader Cable .......................................................................... 23
Figure 44: Unloader Socket ............................................................................................ 23
Figure 45: Operating & Storage Environment for TR7600 SIII ...................................... 24
Figure 46: Plug Type ....................................................................................................... 25
Figure 47: Phase Terminals ............................................................................................ 26
Figure 48: TRI 3-phase Cable Wiring ............................................................................. 26
Figure 49: No Fuse Power Switch .................................................................................. 27
Figure 50: Turn the Power Switch Clockwise to Turn Power On ................................... 27
Figure 51: Change the Plug Type ................................................................................... 28

Test Research, Inc.
1 TR7600 SIII Series User Guide – Installation
1 INTRODUCTION
This manual can be applied to TR7600 SIII.
1.1 Objectives
After you finish reading this manual, you should be able to:
Understand requirements for the system installation.
Prepare the system installation.
Finish the system installation.
1.2 Overview
The whole process of installation includes:
1) System Delivery
2) Container Unpacking
3) Check Accessories
4) Uninstall Mounting Brackets
5) Install X-ray Tube
6) Install Three Color-Light Tower
7) Install Air Supply Cable
8) Install Monitor
9) Input/Output Signal Port (SMEMA)
10) Power Installation
11) Tube Warm Up
12) X-ray Radiation Measurement