3.4 Start of Automatic Operation Refer to "1.3 Start of Automatic Operation" in "Section 3" (the instruction manual (V ol. 1) of the main machine) for details. 3.4 Start of Automatic Operation 0109-00…

100%1 / 223
(10) Press the [READY] button (one of the operation switches).
When the tray is loaded with new components, check for
positional deviations of components and a play of the tray.
Refer to "5.2 "UNIT ADJ." Window (Submenu)" in "Section
2" for details.
Be sure to insert a pallet horizontally. Otherwise, the
pallet cannot be drawn out, causing some components
to be dispersed or the pallet or the feeder to be dam-
aged.
Maximum Mass of Installable Rack
Total mass ((pallet + tray component) × steps) which can install in
rack is up to 45 kg.
Example: Tray Components of 600 g
(Rack 1 kg + Tray Components 600 g) × 28 = 44.8 kg
Number of Steps Available for Pallets
The number of available steps differ, depending on the height of com-
ponents.
Height of Components Available Number of Steps in Rack
8 mm or less 1 step
8 to 16.5 mm 2 steps
16.5 to 28 mm 3 steps
Component Height for 29- and 30-Step Racks
When the 29- and 30-step racks are used, the component height is
regulated as follows.
The 29-step rack can store only the components of 16.5 mm or less
in height.
The 30-step rack can store only the components of 8 mm or less in
height.
3.3.7 Preparation for P.C.B.'s
In the case of normal automatic operation, confirm that P.C.B.'s are
prepared in the input machine.
Refer to "1.2.3 Preparation for Components and P.C.B.'s" in "Section 3"
(the instruction manual (Vol. 1) of the main machine) for details.
3.3 Preparation before Operation
0311-003 1-23 AHI01EGP
Note
CAUTION
3.4 Start of Automatic Operation
Refer to "1.3 Start of Automatic Operation" in "Section 3" (the instruction
manual (Vol. 1) of the main machine) for details.
3.4 Start of Automatic Operation
0109-001 1-24 AHI01EGP
3.5 Temporary Stop and Restart of Automatic
Operation
3.5.1 Replenishment of Components
There will be two cases of component supply replenishment during au-
tomatic operation - Component Replenishment with Machine in Short of
Components and Intentional Component Replenishment.
Component Shortage Mode
When a component shortage error occurs during automatic opera-
tion, an error alarm is issued and the machine stops.
In this case, follow the steps below to replenish components and re-
start the automatic operation.
Fig. A32 "Machine Information" Window
3.5 Temporary Stop and Restart of Automatic Operation
0109-001 1-25 AHI01EGP