Tg0699-PM-D2 *4 Printing Time This indicates the cumulative period of time during which printing operations were actually performed (from the start to the end). The cumulative period of time does not include the periods …

Tg0699-PM-D2
0207-001 Chapter 1 3-8
2.2 "Time Data" Tab
*1
*2
*3
*4
*5
*6
*7
*8
*9
*10
*11
*12
*13
*14
*15
*16
*17
2.2 "Time Data" Tab
Displayed is the data that represents the cumulative periods of run-
ning time for each operation mode.
••
••
• Sheet Layout
When the "Time Data" tab is pressed in the "MANAGE. DATA 1"
window (submenu), the following tab sheet appears.
Fig. 3C5 "Time Data" Tab Sheet
••
••
• Sheet Composition
*1 Ratio Chart of Operation Time
Each time ratio based on "Power ON Time" (described below in
*2) is classified by colors and charted by columns. The colors in
the chart correspond to those indicated before each name.
Each time ratio is updated every 5 seconds.
*2 Power ON Time
This indicates the cumulative period of time ("*3 AUTO OPN.
TIME" + "*10 Stop Time") during which the control power was
ON.
*3 AUTO OPN. TIME
This indicates the cumulative period of time ("*4 Printing Time" +
"*5 PCB Trans. Time" + "*6 PCB Wait Time" + "*9 Print. Test
Time") during which the object P.C.B.’s were produced.

Tg0699-PM-D2
*4 Printing Time
This indicates the cumulative period of time during which printing
operations were actually performed (from the start to the end).
The cumulative period of time does not include the
periods of time during which the machine is in the
"STOP" or the "PAUSE" mode, the semi-auto operation
is performed, or P.C.B.’s are transferred.
*5 PCB Trans. Time
This indicates the cumulative period of time during which the
P.C.B. transfer motors for the R and L conveyors were activated.
The cumulative period of time does not include the
printing time.
*6 PCB Wait Time
This indicates the cumulative period of time ("*7 Inp. Mach.
Wait" + "*8 Out. Mach. Wait") during which the main machine
was waiting for the input and output machines to transfer or
discharge a P.C.B.
*7 Inp. Mach. Wait
This indicates the cumulative period of time during which the
main machine was waiting for the input machine to transfer a
P.C.B.
*8 Out. Mach. Wait
This indicates the cumulative period of time during which the
main machine was waiting for the output machine to discharge a
P.C.B.
*9 Prin. Test Time
Displayed is the time required to inspect the printing condition of
the P.C.B. This printing condition inspection function is optional.
When the machine is not provided with this function, "0" (zero)
will be set in the "Prin. Test Time" text box.
*10 Stop Time
This indicates the cumulative period of time ("*11 Maint. Stop
Time" + "*12 Error Stop Time" + "*15 Others") during which the
machine was stopped.
0207-001 Chapter 1 3-9
2.2 "Time Data" Tab

Tg0699-PM-D2
0207-001 Chapter 1 3-10
2.2 "Time Data" Tab
*11 Maint. Stop Time
This indicates the period of time during which the machine was
stopped for the following maintenance operations.
• Manual Cleaning of Screen
• Replenishment of Cleaning Solvent
• Replenishment of Cleaning Paper
• Replenishment of Solder Paste
*12 Error Stop Time
This indicates the period of time ("*13 Error Alarm Time" + "*14
Recovery Time") during which the machine was reset to its
normal condition after an error alarm was issued.
*13 Error Alarm Time
This indicates the period of time during which the machine
issued an error alarm.
*14 Recovery Time
This indicates the period of time required for the machine to be
reset to its normal condition.
*15 Others
This indicates the period of time required for setup, program
change, and idling operations.
*16 Test Mode Time
This indicates the period of time during which the machine was
operated in the "TEST" mode (operation mode).
*17 SET-UP Time
This indicates the period of time during which the [OPERATION/
SET UP] switch on the front operation panel was set to the "SET
UP" side.