1 Installation 1-9 Intake-side air coupler 65SN/85SN (Nitto Kohki) or equivalent Air coupler A ir regulato r 0.5MPa

1 Installation
1-8
⑤ After the machine is positioned, make sure that a board runs smoothly between upstream and
downstream conveyor.
⑥ Place a leveler on the X-axis beam and make a fine adjustment so that the difference in indicator when
the X-axis beam moves forward and backward will be within 1 division. ( To prevent a X-axis beam
distortion. )
Viewed from the front
Viewed from the rear
⑦ Lock the adjust foot nut lastly.
NOTE: The adjust foot nuts must be locked with a closed wrench (nominal: 46mm) or a single-head wrench.
⑧ Connect the power cable and ground line independently of other machines which may be a noise
source, such as a compressor, welding machine.
⑨ Connect an intake-side air coupler 65SN or 85SN (Nitto Kohki) or equivalent to the air regulator
coupler located on the rear of the machine. After the coupler is connected, make sure that the air
regulator’s reading is 0.5MPa(5.1 ㎏ f/c ㎡).

1 Installation
1-9
Intake-side air coupler
65SN/85SN (Nitto Kohki) or equivalent
Air coupler
A
ir regulato
r
0.5MPa

1 Installation
1-10
Supplementary Explanation for Installation
When setting up a production line, level adjustment and line positioning of the machine may be carried out
at the same time. However, to fine-adjust the machine position with the machine level, i-PULSE
recommends that the machine be roughly positioned to the production line first, and then be leveled and
positioned accurately using the following four sets comprising a hydraulic jack and plates.
ACTION:
① Apply grease between base plates 1 and 2 for lubrication purposes.
② Place a plate set near each machine jack-up point (four points).
③ Place a jack on each plate set and jack up the machine.
④ Adjust each jack so that the machine is level.
⑤ Fine-adjust the position of the machine while the machine is jacked up. (The machine can be moved
lengthwise and crosswise with help of grease applied between the plates.)
Hydraulic jack
Base plate 1
Base plate 2
Apply grease
between the
p
lates.
Hook stroke