X-Feeder Upgrade Install Replace parts of the rocker 32 AI X-Feeder Upgrade Package AI X-Feeder Upgrade Packa ge 3.6 3 . 6 R e p la c e p a r t s o f t h e r o c k e r Replace parts of the rocker 3.7 3 . 7 F it t in g t …

100%1 / 38
X-Feeder Upgrade Install
Replacing the stuffing gear and parts of the cover strip rocker
AI X-Feeder Upgrade Package AI X-Feeder Upgrade Package 31
3.5
3.5 Replacing the stuffing gear and parts of the cover strip rocker
Replacing the stuffing gear and parts of the cover strip rocker
Tools required:
Hexagon socket Gr. 2
Phillips screwdriver
Flat bladed (slotted) screwdriver
Tweezers
(1) Loosen the screws marked in the figure, at the top
and bottom of the stripping device. Depending on the
width of the feeder module, there will be up to a total
of 4 screws to be loosened at the top and bottom.
(2) Loosen the screws on the cover sheet of disposal
drive.
Lift the cover plate off the foil disposal drive.
(1) Lift the gear stages with tweezers from the foil dis
-
posal drive.
Attention: The stage gear is greasy!
(2) Remove the knurled stuffing gear and replace it
with the new "interlocked complete stuffing gear."
Make sure that the corresponding washers are on the
toothed wheel axes (1).
Place the cover plate on the slide disposal drive.
Make sure that the cover plate engages on the
toothed wheel axes (2) and the cover plate lies flat
level on the side cover.
Fix the cover plate with the countersunk screws
marked in the diagram.
X-Feeder Upgrade Install
Replace parts of the rocker
32 AI X-Feeder Upgrade Package AI X-Feeder Upgrade Package
3.6
3.6 Replace parts of the rocker
Replace parts of the rocker
3.7
3.7 Fitting the Flap Tape Disposal
Fitting the Flap Tape Disposal
(1) Screw the new scraper plate, with the original
screws, slide the drive disposal, starting with the
overhead screws.
Install the new folding roller (2) with the original shaft
and screw.
Insert the "use foil wing" (3) and mount it with the orig
-
inal wave.
Caution! The originally present role is not needed and
is omitted.
Tools required:
Phillips screwdriver
Flat bladed (slotted) screwdriver
(1) Remove the marked in the figure bearing shaft
from the old rocker.
Insert the new stuffing gear (3) as shown in the new
rocker (4) and secure it with the previously removed
bearing shaft (2). Make sure that the stuffing gear can
move freely in the rocker.
Insert the new wiper sheet (5) and secure it with the
screws, starting with the overhead screws.
Open the flap.
Replace the existing door carefully from the feeder.
Place the new cover slowly in a foil container. The
spring (1) it is overridden. It is not necessary since the
function is now performed by the magnet (2).
X-Feeder Upgrade Install
Cover foil disposal install
AI X-Feeder Upgrade Package AI X-Feeder Upgrade Package 33
3.8
3.8 Cover foil disposal install
Cover foil disposal install
Tools required:
Phillips screwdriver
TORX screwdriver size T8
(1) Press the foil disposal drive in the direction of the
arrow and into the foil container.
Attach the film drive with the marked cylinder head
bolts. Be sure to insert the shims.
(2) Fix the foil disposal drive into place with the cylin
-
der head screw marked in the diagram.
(3) Turn the foil disposal to drive again and attach the
spacer to the marked in the figure Torx screws. Note
the correct position of the rubber seals (4).
(1) Carefully place the feeder module down on its left
side. Position the foil container so that it is aligned
against the side cover.
(2) Loosen the screws marked in the diagram.
(1) Insert the flat ribbon cable into the connection, as
far as the stop. Make sure that the blue surface at the
end of the cable is at the top and that the flat ribbon
cable lies straight in the connection. Swing the lock
down onto the flat ribbon cable.
(2) and (3) Carefully insert the connector in the direc
-
tion of the arrow, as far as the stop, into the connec
-
tion shown.
(4) Insert the other connector into the connection
marked in the diagram.