00196614-03_AI_Vakuumpumpe_SXDX12_de_en - 第112页
Fitting the Vacuum Pump Installing the Vacuum Pump 3.4.5 Closing the Installation Location 112 Vacuum Pump Vakuumpumpe 3.4.5 3 . 4 . 5 C lo s in g t h e I n s t a lla t io n L o c a t io n Closing the Instal lation Locat…

Fitting the Vacuum Pump
3.4.4 Connecting the Exhaust Tube ID100 [03087599-xx] Installing the Vacuum Pump
Vacuum Pump Vakuumpumpe 111
3.4.4
3.4.4 Connecting the Exhaust Tube ID100 [03087599-xx]
Connecting the Exhaust Tube ID100 [03087599-xx]
► Lift the vacuum pump and push in the air outlet con-
duit. It will engage into its end position on the assem-
bly plate.
► Screw the air outlet conduit on the left and right to the
fixture points shown before.
► You may want to have a flashlight ready to see your
workplace better.
► Fit the spanner wrench provided to the vacuum
pump, as shown in the diagram.
► Adjust the exhaust tube to a length of 120 cm.
► Position the exhaust tube onto the connecting piece
and run the hose along the side of the machine base
and out of the machine.
► Fasten the hose with a hose clamp Ideal Maxi W1
[03090050-xx] to position (1).

Fitting the Vacuum Pump
Installing the Vacuum Pump 3.4.5 Closing the Installation Location
112 Vacuum Pump Vakuumpumpe
3.4.5
3.4.5 Closing the Installation Location
Closing the Installation Location
► After fitting the pump, close the installation point with
the "cover plate assembly / P001" [03088818-xx].

Fitting the Vacuum Pump
3.5.1 Conversion for C&P20 A/P Converting Placement Heads
Vacuum Pump Vakuumpumpe 113
3.5
3.5 Converting Placement Heads
Converting Placement Heads
3.5.1
3.5.1 Conversion for C&P20A/P
Conversion for C&P20 A/P
▪ Conversion kit for vacuum pump operation C&P20 [00119790-xx]
Original state - C&P20 A/P for compressed air operation
NOTICE
Restrictions for TwinHead or CPP head on the gantry to be converted
The TwinHead and CPP placement heads are not compatible with vacuum pump operation. Do
not convert the pneumatic supply for the gantry affected to vacuum mode. If the compressed
air supply for this head is converted to vacuum operation, the return cylinder will be unable to
move out and the Z axis will remain in its top position.
CAUTION
Conversion from C&P20 A/P head to TwinHead or CPP head
If you need to convert a gantry from C&P20 A/P to TwinHead or CPP head, you must re-estab-
lish the original compressed air supply for this gantry. Conversion reversal must be performed
on all assemblies for this gantry. Partial conversion of the pneumatic unit, for example, involving
disconnection of the gantry hoses (additional vacuum hoses) during compressed air opera-
tions, can lead to serious placement machine malfunctions.
CAUTION
Conversion from TwinHead to C&P20 A/P head with vacuum operation
If you need to convert a gantry with TwinHead to C&P20 A/P head with vacuum function, you
must retrofit the vacuum equipment for this gantry. If you operate a C&P20 A/P head which has
been converted for vacuum operation at a gantry with compressed air, this could lead to serious
damage to the placement head if the silicon hoses to the segments should loosen.
CAUTION
Preparatory work
After you have properly shut-down the operating system: turn the machine off at the main
switch and isolate it from the mains, before you perform any work to the machine. In addition,
the compressed air supply must be turned off at the main valve of the compressed air unit, in
the machine base, and the compressed air lines must be bled by actuating the needle valve on
the compressed air unit. See also "1.2 Preparatory Work..." [ ➙ 73].