1.1.6 Safety Instructions on Hazardous Materials Preparatory Work...
Interior Lighting Innenraumbeleuchtung 33
Lockout attachment [03121545-xx]
Attaching the lockout attachment [03121545-xx]
Example 1: Securing the machine with a lockout at-
tachment
The lockout attachment can prevent the machine
from being switched on inadvertently.
Switch off the machine.
Set the circuit breaker to OFF.
CAUTION!
The lockout attachment may only be attached when
the machine is switched off!
Attach the lockout attachment (1) to the circuit
breaker.
Secure the circuit breaker with a padlock.
Introduction
Preparatory Work... 1.1.6 Safety Instructions on Hazardous Materials
34 Interior Lighting Innenraumbeleuchtung
Alternative: Attaching warning signs:
If a machine can be locked, it must be.
However, there are situations where energy isolating devices cannot accommodate locks. In these
cases, the energy isolating devices must be tagged to warn employees that the machine is de-ener-
gized for servicing. The tag or label must be securely fastened, it must be placed in a position visible
to all and it may only be removed by the person who attached it.
Release of stored energy:
Stored energy in the compressed air supply or electrical energy in electrolytic capacitors must be
released by appropriate means.
After switching off the machine, wait until the voltages and the compressed air have discharged, so
that work can be performed without any risk.
Testing the lock out:
The lock can be easily tested by pressing the START button.
The following steps must be taken to restore the machine to operation.
Check the working area. Authorized employees should remove all of their tools and reinstall all safety
features.
Notify all affected employees.
Before removing even one lock or tag, inform all workers in the affected area that the machine is
going to be restarted.
Remove all locks/tags.
Every authorized employee must remove his own lock and shut it away.
Turn the machine on. Make sure that authorized staff check the equipment in operation to ensure
that repairs were performed correctly
Attaching a padlock to the motor contactor
Example 2: Attaching a padlock to the motor
contactor
Turn the operating lever (1) counterclock-
wise.
Use the screwdriver to push the locking
lug (2) out of the operating lever (1).
Secure the operating lever with a padlock
(3).
Introduction
1.1.6 Safety Instructions on Hazardous Materials Preparatory Work...
Interior Lighting Innenraumbeleuchtung 35
Testing
Service personnel may test circuits by energizing them briefly without suspending the Lock Out / Tag
Out Procedure. This may only be done when no other work is being performed by any other person on
the equipment being tested.
It is extremely important that all remote START switches be tagged with the "Do Not Operate" tag to pre-
vent inadvertent operation of the equipment during these periods.
Responsibilities
It shall be the responsibility of the maintenance and service personnel to make sure this procedure
is adhered to.
It shall be the responsibility of the maintenance and service personnel's immediate supervisor to in-
struct his personnel on this procedure.
It shall be the responsibility of the Safety Officer with assistance from the Safety Committee, Health
Service Department, and the various managers and vice-presidents to administer the Lock Out / Tag
Out Procedure.