1 Installation 1-2 Installation of Mounter Environmental Requirements Install the mounter where th e below conditions are met. Do not do tasks, such as moving the machine or connecting the machine with the main switch ON…

100%1 / 48
1 Installation
1-1
1
Installation
1 Installation
1-2
Installation of Mounter
Environmental Requirements
Install the mounter where the below conditions are met.
Do not do tasks, such as moving the machine or connecting the machine with the main switch ON to
prevent electric shock.
Ambient Temperature: 15 to 35 degrees C
Relative Humidity: 45 to 60 percent, non-condensing
Atmosphere: Dust and corrosive gas free
Floor: Floor must be flat and sturdy enough for freedom from vibration during
operation.
Power Requirements: 200 VAC +/- 10%, three phase, 50/60 Hz
* 208/220/230/240/380/400/415/440 VAC with optional power
transformer
Power consumption: 2 kW
Capacity: 5 kVA
Leakage current: 100mA or less
* Power and ground the machine independently of other machines which may be a
noise source, such as a compressor, welding machine, or reflow soldering machine
with magnetic contacts.
Warning
1 Installation
1-3
Production Line
To align your assembly line, first install the heaviest unit. Then install peripheral units using the first unit as
a reference.
Reference
Loader     Mounter     Reflow Oven   Conveyor Unloader
To transfer the PCB (printed circuit board) smoothly, clearance between units are quite important. Be sure
that the clearance between units is approximately 5 mm as below figure shows. Adjust the height of the
downstream unit a little lower (0-0.5 mm) so that the PCB is transferred smoothly.
0 - 0.5mm
Approx. 5mm
DownstreamUpstream