semi合集-English.pdf - 第4252页

SEMI F78-0304 © SEMI 2003, 2004 5 may contaminate the tub ing being faced. The cutting or facing shall not be of a abrasi ve type. 8.7 Severing or parting equip ment shall be of the machining type that will sep arate the…

100%1 / 7923
SEMI F78-0304 © SEMI 2003, 2004 4
5.1.54 tungsten — non-standard term for tungsten
electrode.
5.1.55 tungsten electrode (2) — a component of the
electrical circuit that terminates at the arc, molten
conductive slag, or base metal. A non-filler electrode
made principally of tungsten and used in arc welding.
5.1.56 undercut (2) — a groove adjacent to the base
metal at the edge of the weld left unfilled by weld
metal.
5.1.57 underfill (2) — a groove weld condition in
which the weld face or root surface is below the
adjacent surface of the base metal.
5.1.58 weld bead (2) — a weld resulting from a weld
pass.
5.1.59 weld level — a segment or portion of a weld
schedule in which one or more weld parameters can be
changed independently; part of a weld sequence.
5.1.60 weld sequence — a series of steps executed by
the welding power supply to make a particular orbital
weld.
5.1.61 welder — a person who does welding
(sometimes used to refer to a welding machine or
power supply).
5.1.62 welding equipment — power supply, weld
heads, torches, and associated cables and accessories
used for welding.
5.1.63 welding operator — a person who welds with
an orbital or machine welding system.
6 Summary of Practice
6.1 The welding procedure is shown in the flow chart
in Figure 1.
7 General Requirements
7.1 All welding performed under this practice shall
conform to the applicable requirements of the ASME
Boiler and Pressure Vessel Code, Section IX, ANSI
B16.25, B31.3 Chapter V, and AWS B2.1, to the extent
that they are included herein.
7.2 All welds shall be based upon Welding Procedure
Specifications (WPS) and be documented with
associated Procedure Qualification Records (PQR) in
accordance with ASME Boiler and Pressure Vessel
Code, Section IX, or with AWS B2.1.
7.3 Qualification of the welding procedures to be used,
and of the performance of welders and welding
operators, shall conform to the requirements of the
ASME Boiler and Pressure Vessel Code, Section IX,
Articles II and III, or AWS B2.1.
7.4 All welding shall be performed only by certified
welders and welding operators. Certification procedures
shall include, at the minimum, producing three
acceptable welds in a row of typical GTA weld joints of
the smallest and largest diameters of each alloy to be
welded. Welding parameters shall be set by the welder
or welding operator. Certification shall expire after six
months of inactivity.
7.5 The weld assembly shall be kept under a
continuous purge until all welding is complete.
7.6 Welders shall use clean room-compatible gloves
any time that the tubing or component to be welded is
removed from protective covering.
8 Apparatus
8.1 Welding equipment shall be of the GTAW,
constant current, DCEN (direct current electrode
negative) and electronically controlled type with rapid
dynamic response capable of 5 Hz (CPS) or greater
pulsed welding.
8.2 All welding fixtures and weld heads shall be clean
and free of any particulate and excessive discoloration.
Weld heads shall rotate freely and smoothly at all
speeds. All clamping and holding fixtures shall fit
tightly around applicable fittings/tubing, allowing no
movement after clamping in excess of 0.003 inch
(0.008 cm). The welding fixturing shall allow viewing
of the weld joint to insure proper fit-up.
8.3 Electrodes shall be precision ground to the factory
specification for head and weld type. Electrode gap
shall be set using tooling or procedures that provide
accurate and repeatable gaps to be set to within 0.002
in. (0.005 cm). The use of 2% Ce-doped or 2% La-
doped tungsten electrodes is recommended.
8.4 Purge gas apparatus shall be stainless steel tubing
and components with face seal fittings, when possible.
PFA plastic tubing is acceptable as the final run to
allow flexibility for hook-up. Lengths shall be restricted
to less than ten feet. All components that come into
contact with the weldment shall be stainless steel. Only
heavy wall PFA or stainless tubing shall be used on the
ID purge. Only stainless tubing shall be used on HP
systems.
8.5 Purge gas flow shall be measured and controlled.
8.6 Facing equipment shall be of the dry end
machining style. The equipment shall be capable of
tolerances of 0.003 inches from a plane perpendicular
to the centerline of the tube, the OD and /or ID burr of
less than 0.005 inches. The equipment shall be capable
of controlling the cut curl so as that it does not enter the
tubing or cause scratching of the ID surface. The
equipment shall not use oils or lubricants in a way that
SEMI F78-0304 © SEMI 2003, 2004 5
may contaminate the tubing being faced. The cutting or
facing shall not be of a abrasive type.
8.7 Severing or parting equipment shall be of the
machining type that will separate the tubing without
contaminating the ID of the tubing. Wheel type cutters
designed to cut stainless steel and CRAs are allowed
with purge. Dry saws of orbital type or cutoff are
allowed only when followed by cleaning to 12.5. All
cut ends shall meet the tolerances for facing equipment
or be followed by end preparation with a facing tool.
9 Materials
9.1 All materials to be welded shall be manufactured to
ASTM specifications and so certified by the
manufacturer. Certification shall conform to ASTM
A450, Section 25.
9.2 All seamless austenitic stainless steel tubing shall
be in conformance with SEMI F20 or customer
specification.
9.3 A backing (ID) gas is required during welding, and
while tacking (if tacking is used).
9.4 Weld parameters are affected by the choice of
shield gas. Argon, due to its effectiveness and material
compatibility, is the most commonly selected shielding
and purging gas. Argon and helium are inert and
therefore have no effect on the weld metal. These gases
do have very different ionization potentials, thermal
conductivity, and reactivity.
9.5 Argon/hydrogen mix is a reducing gas that avoids
the formation of oxides. It also reduces the amperage
required for a given ID weld bead width while reducing
the OD bead width. Argon/hydrogen mixes adversely
affect high ferrite materials (above 80% ferrite). Use of
argon/hydrogen mixes will shorten tungsten electrode
life. The weld parameters will be affected by hydrogen
to argon percentages. Hydrogen mixes above 5 vol%
are not recommended for safety reasons.
9.6 Nitrogen will cause instability of the arc in mixes
above 3 vol% in the shield (OD) purge gas. It is a
acceptable backing (ID) gas for austenitic stainless and
many CRAs. Nitrogen when exposed to welding
temperatures will cause nitride formation in some high
ferrite materials (above 80% ferrite). Use of nitrogen
mixes in the shielding (OD) gas will shorten the
tungsten electrode life.
9.7 The ID purge gas will be certified to 99.9997%, or
less than 3 ppm total contaminants (moisture, oxygen,
and other contaminants).
10 Safety Precautions
10.1 This practice does not purport to address all of the
safety issues associated with its use. It is the
responsibility of the users of this standard to establish
appropriate safety and health practices and determine
the applicability of regulatory limitations prior to use.
10.2 Welding equipment used to make welds shall be
operated in accordance with the manufacturer’s
operating and safety instructions.
10.3 All welding performed under this practice shall
conform to the applicable requirements of ANSI/ASC
Z49.1.
10.4 Welding gas mixtures containing more than
5 vol% H
2
are not recommended due to the potential for
fire hazard.
10.5 Do not reweld stainless steel that has been used
for corrosive gas delivery.
10.6 See Appendix 1 for information on stainless steel
and welding fume.
11 Test Specimens: Couponing
11.1 Prior to the welding of a particular size, wall
thickness, and alloy, a primary standard sample weld
shall be made, sectioned, and analyzed at the job site.
The primary standard sample weld shall become the on-
site work sample against which other welds of the same
size, wall thickness, and alloy are judged. This on-site
work sample may be used indefinitely or reproduced
each day at the discretion of the examiner.
11.2 The primary standard sample weld shall be
checked for compliance with SEMI F81, “Specification
for Visual Inspection and Acceptance of Gas Tungsten
Arc (GTA) Welds in Fluid Distribution Systems in
Semiconductor Manufacturing Applications.” Coupons
shall be cross-sectioned and inspected visually. Weld
coupon criteria are the same criteria for all system
welds.
11.3 Once a sample weld is found to be acceptable, all
essential and supplementary essential variables shall be
documented in the procedure qualification record.
11.4 Any significant deviation(s) from the on-site
work sample will cause the weld(s) to be rejected.
Rejected welds shall be removed and replaced.
11.5 Sample test welds shall be made periodically.
These sample test welds shall be compared to the on-
site work sample and checked for compliance with
SEMI F81. Deviation from the on-site work sample or
SEMI F81 shall be cause for rejection. If the weld
inside diameter is inspectable using a sight tube or other
device, sample test welds may be production welds.
SEMI F78-0304 © SEMI 2003, 2004 6
Sample test welds shall be made when any of the
following conditions exist:
11.5.1 Start of shift (in) or end of shift (out).
11.5.2 Change of weld parameters.
11.5.3 Change of material (heat number).
11.5.4 Change of tube size or wall thickness.
11.5.5 Change of ambient temperature ± 20°F
(± 11°C).
11.5.6 Change of source of power to power supply to
include addition or subtraction of extension cords.
11.5.7 Change or removal of the weld electrode.
11.5.8 Any change of equipment such as weld head,
weld head extensions, or power supply.
11.5.9 Any time that a weld discrepancy is noted by
the welding operator.
11.5.10 Any significant change of ID or OD purge gas
(source or flow rate).
11.6 All couponing shall use the same ID purge gas
and OD shielding gas as the production weld (Figure 2).
12 Procedure
12.1 Documented procedures shall exist for each weld
configuration including all parameters (including purge
times, orifice sizes, purge rates, and internal pressure).
12.2 Check parameters and verify that they are in
accordance with the qualified welding procedure.
12.3 Perform only one weld joint at a time.
12.4 Joint Preparation Procedure
12.4.1 All cutting of component or tubing weld ends
shall be done with a sharp-edged tool. No lubricants of
any kind shall be allowed.
12.4.2 All component and tubing weld ends shall be
de-burred after cutting.
12.4.3 Surfaces for welding shall be clean and shall be
free from oxidation, discoloration, oil, scale, chips, or
other material that is detrimental to welding.
12.4.4 Unless tubing is to be cleaned afterward, tubing
shall be opened, cut, faced, and deburred in a required
cleanroom environment, leaving no visible particulates
inside the cut end.
12.4.5 The tube shall be faced to remove all
necking/wedging caused by the tube cutters (Figure 3).
For tube cutting, use a wheel cutter with lathe-type
facing tool or a special designed power saw with
alignment guide. Do not use lubricant. If any “nicks”
are found, reface or discard the tube.
12.4.6 Unless tubing is to be cleaned afterward, all
weld end preparation shall be done in such a manner as
to minimize the introduction of contaminants into the
system. When bending, cutting, or facing tubing a
positive purge must be used to remove any particles.
12.4.7 The prepared end shall conform to ASTM A
632 (or ASTM A 269 ½ in. OD) tubing specification
with regard to ovality and wall thickness.
12.4.8 The weld fit-up gap shall not exceed 0.003 in.
(0.08 mm) when the entire circumference is affected
(Figure 4). The maximum gap in any one area shall not
exceed 0.006 in. (0.15 mm) (Figure 5). The prepared
end shall be square to tube run within ¼° (angle).
12.4.9 After preparing, debur the inside diameter
carefully and lightly. Do not scratch the inside
diameter. Any scratched tubes shall be reprepped or
scrapped.
12.4.10 Chamfering is undesirable. The maximum OD
or ID chamfering shall be less than 10% of the wall
thickness or 0.005 in. (0.13 mm) whichever is less
(Figure 6).
12.4.11 All components shall be maintained in a clean
condition until welded into the system.
12.4.12 All benders, cutters, facing tool collets, or
brushes that are to be used on stainless tubing or alloy
tubing shall not be used on carbon steel tubing and care
shall be used on mixing alloys. All tools shall be
maintained in clean condition and shall be free of
grease, oil, dirt, and other foreign matter. Avoid cross-
contamination from dissimilar materials.
12.4.13 Bends on the tubing shall not be made in the
weld area.
12.4.14 Use only tools and handling techniques that
will not mar, disturb the shape of, or in any way reduce
the conformance to specifications of the materials used
in this system.
12.4.15 Tube ends shall be covered while the purge is
removed using a technique that will minimize the
amount of infiltration or contamination. Covers shall be
of non-particulating material.
12.4.16 Remove protective cover immediately prior to
performing the weld.
12.5 Tube Cleaning
12.5.1 It is recommended that all cut tubing be cleaned.
At a minimum, tubing contaminated during preparation
shall be cleaned using a high purity cleaning procedure.