4OM-996-007 - 第136页

1.4 Maintenance Method (2) When the [Start Oil Supply] button is pressed in the "Oil Supply" tab sheet, the following sheet appears. Fig. 4A85-2 (3) Press the [ALL] button (entitled "ZERO"). In two se…

100%1 / 417
1.4 Maintenance Method
1.4.9 Lubrication of Linear Guide in Feeder Carriage Section
Grease should be applied every 6 months after the initial month.
Preparation for Lubrication
(1) Turn off the power supply to the machine and wipe off old grease
on the rail of the linear guide with a rag.
(2) Prepare the FL- and P-type attachments.
The combination of the U- and P-type attachment can also be
used for lubrication from the front side of the machine.
Fig. 4A85
Lubrication Procedure
The linear guide in the feeder carriage section must
be lubricated with the [POWER ON] button on the
operation panel being pressed ("ON" condition).
It is dangerous. Be sure to lubricate alone (without
any other attended personnel).
(1) Press the [UNIT ADJ.] button on the submenu bar that appears after
the [MAINT.] button is selected.
When the [Oil Supply] tab is pressed in the "Fdr Crg" tab sheet, the
following tab sheet appears.
Fig. 4A85-1 "Oil Supply" Tab Sheet
CAUTION
FL Type
P Type
U Type
0509-004 1-69 AIM01ETRP
Note
1.4 Maintenance Method
(2) When the [Start Oil Supply] button is pressed in the "Oil Supply" tab
sheet, the following sheet appears.
Fig. 4A85-2
(3) Press the [ALL] button (entitled "ZERO"). In two seconds, press the
[ENABLE] button on the operation panel. All devices are zeroed.
(4) Press all the buttons (entitled "FEEDER READY").
(5) Press the [ON] button entitled "MOVE". In 2 seconds, press the [EN-
ABLE] button on the operation panel.
All axis automatic tuning takes place and the following sheet ap-
pears. (The feeder carriage moves slightly.)
0305-001 1-70
AIM01ETRP
1.4 Maintenance Method
(6) Press the [ON] button entitled "MOVE". In 2 seconds, press the [EN-
ABLE] button on the operation panel.
The feeder carriage moves to the grease supply position and the
following sheet appears.
Fig. 4A85-3
(7) Press the [EMERGENCY STOP] switch and open all the doors.
Apply grease to the nipples on the slide blocks of linear guides.
After that, close all the doors.
(8) Unlock the [EMERGENCY STOP] switch and press the [RESET]
button. Press the [POWER ON] button to power the machine.
Press the [ALL] button (entitled "ZERO"). In 2 seconds, press the
[ENABLE] button on the operation panel.
0305-001 1-71