NPM Maint en anc e E di ti on EJM9BE-M B-09M-21 Page 9-1 9. Calibration This chapt er descr ibes the ca libration p rocedures. Calibrat ion refers to the adjustm ent for setting the param eters in order to co rrect the i…

100%1 / 99
NPM
Maintenance Edition
9. CALIBRATION ............................................... 9-1
9.1 NPM Calibration Items and Procedures ...............................................................9-2
9.1.1 Calibration Items ........................................................................................................................... 9-2
9.1.2 Jigs to be Used for Calibration....................................................................................................... 9-3
9.1.3 Common Procedure ...................................................................................................................... 9-4
9.1.4 Explanation of the Calibration Menu Screen .................................................................................. 9-4
9.2 Head Camera XY Origin.......................................................................................9-5
9.3 Plane Compensation XY.......................................................................................9-7
9.4 Head / Plane Compensation Z ...........................................................................9-12
9.5 Width Adjustment................................................................................................9-17
9.6 Placement Position / Conveyor ..........................................................................9-20
9.7 Placement Load..................................................................................................9-31
9.8 Line Camera .......................................................................................................9-49
9.9 Jig Station ...........................................................................................................9-57
9.10 3D Camera........................................................................................................9-65
9.11 Height Offset.....................................................................................................9-73
9.12 Vertical Line Camera.........................................................................................9-79
9.13 Tray...................................................................................................................9-83
9.14 Accuracy Verification.........................................................................................9-87
9.14.1 Overview...............................................................................................................................................9-87
9.14.2 Detailed Processes...........................................................................................
....................................9-90
NPM
Maintenance Edition
EJM9BE-MB-09M-21 Page 9-1
9. Calibration
This chapter describes the calibration procedures.
Calibration refers to the adjustment for setting the parameters in order to correct the
individual differences from machine to machine.
Perform calibration in the following cases:
After the machine has been relocated
After the replacement of unit(s)
If the floor level has been changed
Calibration requires the following time:
12-nozzle head (front/rear) specification: About 60 minutes
2-nozzle head (front/rear) and tray feeder specification: About 60 minutes
NPM
Maintenance Edition
9.1 NPM Calibration Items and Procedures
Page 9-2 EJM9BE-MB-09M-21
9.1 NPM Calibration Items and Procedures
NOTICE
Observe the following when performing calibration.
Turn ON the main power switch of the machine at least 1 hour before starting
calibration.
Do not perform warm-up operation before starting calibration.
After the machine has been stopped during production or warm-up operation, wait
more than 3 hours before starting calibration.
9.1.1 Calibration Items
The table below shows the calibration items and the items to be performed in response to the changes in
machine conditions (relocation, unit replacement, etc.).
Changes in machine condition and
calibrations to be performed
STEP Menu Sub-menu
Relocation,
change in
floor level
Addition of
3D sensor
2
Replacement
of head
2
Camera angle c
H-camera XY org
XY Origin Camera scale
c
STEP 1
PlaneCorrXY
PlaneCorrXY
1
c
Measure height c
c
Head/PlaneCorrZ
PlaneCorrZ
1
c
Width adjusting Std width move
Mnt Pos/Conv Measure height
STEP 2
Mount load Load meas(F1)/(F2)
H
θ
axis origin
L-camera
Camera offset
ScanPos. c
c
c
Changer H c
c
c
HCMR Light c
c
c
PCMR Light c
c
c
Jig station
HeadOffset
c
c
c
Height Scale
(
c
)
c
(
c
)
ScanPos.
(
c
)
c
(
c
)
STEP 3
3DCamera (Option)
HeadOffset
(
c
)
c
(
c
)
Height offset Pickup c
VerticalCamera (Option)
Camera offset
(
c
)
(
c
)
Pickup
(
c
)
Pickup pos. 1
(
c
)
STEP 4
Tray
Pickup pos. 2
(
c
)
Placement accuracy
Reflection
c
c
c
Accuracy
Verification
Placement accuracy
Verification
c
c
c
c
: To be performed
(
c
): To be performed only for the machines with that option
1: When the machine is equipped with the dual conveyor, it is necessary to change to the
single lane mode.
2: Perform calibration only for the table where the unit has been replaced.