2OM-1751-003w_G5S - 第166页

2OM-1751 2-44 1303-001 1st speed DCLR SET The speed reduction rate for the backup base rst stage operation in the PCB positioning, is setup in this data box. This value is reected on the speed and acceleration. 2nd spe…

100%1 / 380
2OM-1751
2-43
2nd speed DCLR SET
The backup base operation speed reduction rate is set in this text box.
This value is reected on the second operation in the 2-stage operation in
the PCB positioning, and rst operation in the 2-stage operation in the PCB
releasing.
Backup axis DN start DLY
The time period for the Z-clamp releasing operation completion after the
component placement completion, is set in this text box. After this operation
is completed, the backup base starts moving down.
(D02_06)
SW POSN of 1st / 2nd
The change position between the "First Speed" and "Second Speed" is set in
this data box.
(D02_07)
Replace vacuum sensor
The sensor to be used for vacuum pick-up is selected in this data box.
This function is used when the vacuum judgment threshold value is to be
changed.
Sensor #1
: When selected, the vacuum pick-up is performed using the
sensor #1.
Sensor #2
: When selected, the vacuum pick-up is performed using the
sensor #2.
(D02_08)
PCB position of contact
The offset from the transfer position (moving up rst stage/moving down
rst stage target position) is setup. The value for carrier thickness, etc., is
input as upper direction value (plus value).
(D02_09)
UP
MOVE
"Standard" or "Value Designation" is selected for the PCB positioning
moving up operation.
Normally, "Standard" is selected.
Standard
: The operation is performed based on the standard
values set in the machine.
Value Designation
: For the operation procedure, the selected values
can be setup.
1303-001
3.4 Control
2OM-1751
2-441303-001
1st speed DCLR SET
The speed reduction rate for the backup base rst stage operation in the PCB
positioning, is setup in this data box. This value is reected on the speed and
acceleration.
2nd speed DCLR SET
The speed reduction rate for the backup base second stage operation in the
PCB positioning, is setup in this data box. This value is reected on the
speed and acceleration.
Vac. Ctrl. delayed starts
The time period from the backup base rst stage operation start-up in the
PCB positioning to the vacuum pick-up turning ON, is set in this data box.
Vac. Wtg. Timer
The time period from the backup base rst stage operation start-up in the
PCB positioning to the second stage operation start-up, is set in this data box.
Z clamp waiting time
The time period for judging for the Z-Clamp Moving-up Completion in the
PCB positioning, is set in this data box.
(D02_10)
DN
MOVE
"Standard" or "Value Designation" is selected for the PCB positioning
moving -down operation.
Standard
: The operation is performed based on the standard
values set in the machine.
Value Designation
: For the operation procedure, the selected values
can be setup.
1st speed DCLR SET
The speed reduction rate for the backup base rst stage operation in the
PCB positioning clearance operation, is setup in this data box. This value is
reected on the speed and acceleration.
2nd speed DCLR SET
The speed reduction rate for the backup base second stage operation in the
PCB positioning clearance operation, is setup in this data box. This value is
reected on the speed and acceleration.
3.4 Control
2OM-1751
2-45
Vac. Ctrl. delayed starts
The time period from the operation start-up in the PCB positioning clearance
operation to the vacuum pick-up turning OFF, is set in this data box.
Vac. Wtg. Timer
The time period from the rst stage operation completion to the second stage
operation start-up in the PCB positioning clearance operation, is set in this
data box.
Damaged Vac. Wtg. time
The time period of the vacuum breakage ON operation in the PCB
positioning clearance operation, is set in this data box.
Backup axis DN start DLY
The time period until the backup base rst stage operation start-up in the
PCB positioning clearance operation, is set in this data box.
1303-001
3.4 Control