※ W arnings and cautions fo r safe ty For the safe use of this machine, t he label for safety related cautions is attached at the following position. Inside of the machine For more details about the label for cautions ab…

100%1 / 94
Warnings and cautions for safety
For the safe use of this machine, the label for safety related cautions is attached at
the following position.
Front view of the machine
For more details about the label for cautions about safety, refer to the
Administrator's Guide.
Rear View of the Machine
Warnings and cautions for safety
For the safe use of this machine, the label for safety related cautions is attached at
the following position.
Inside of the machine
For more details about the label for cautions about safety, refer to the
Administrator's Guide.
Operation of the safety interlock
Stop operation of the machine immediately should an emergency situation arise.
1. EMERGENCY Switch
2. Door Lock Switch
DECAN S1 Operation Handbook
Table of Contents
Chapter 1
Machine Overview
Name of Each Part .....................................................1-1
Name of the Operation Panel ................................... 1-2
Configuration of MMI............................................... 1-3
Overview ...................................................................... 7
Chapter 2
Supplying Power and Warming up
Procedure Preparing for Production .......................... 2-1
Chapter 3
Production
Preparation For Operation .................................... 3-1
Preparation For Operation .................................. 3-12
Production ...............................................................3-24
Chapter 4
Items to be inspected during production
Items to be inspected during production ................. 4-1
Take measures of instantaneous stop ....................... 4-3
Temporary stop .........................................................4-9
Emergency Stop ......................................................4-13
Next Generation, Multi-Functional Placer
DECAN S1 Operation Handbook
Chapter 5
Finish production and change work
Finishing Production .................................................. 5-1
SMT In-Line Process ..................................................5-4
Changing Jobs ..........................................................5-5
Chapter 6
Check others and replace exhausted parts
Checking Feeder ....................................................... 6-1
Arranging Backup Pins .............................................6-11