Packing Packing the inspection system 243 Inspection system X7056 | Operating manual | Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a 4. Set the inspection system in a ho rizontal position as indicated by the level. 5. T…

Packing
Packing the inspection system
242
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
Securing the lift door
Perform the following work steps:
1. Open the front lift door.
2. Place two cardboard corners between the lift door and the
inspection system and fasten them with packing tape.
The lift door is secured.
Setting the system feet
To prevent damage to the system during transport, turn the
system feet out as far as they go.
Required: 30 mm open-end wrench
Carpenter's level
Perform the following work steps:
1. Loosen the lock nuts on the system feet.
The feet can now be turned in or out by their lower bolts.
2. Turn the system feet out to a height of 8 - 10 cm.
3. Check with a level to make sure the inspection system is hori-
zontally level.
Lock nut
Screw

Packing
Packing the inspection system
243
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
4. Set the inspection system in a horizontal position as indicated
by the level.
5. Tighten the lock nuts well to secure the system feet.
The system feet are set.
Fastening the inspection system
To prevent damage to the inspection system during transport,
fasten it to the wooden pallet. This chapter describes how to fasten
the inspection system, step by step.
This section covers the following themes:
Inspection system fastening points (Page 243)
Fastening the inspection system to the pallet (Page 244)
Inspection
system
fastening
points
The inspection system is fastened to the pallet at its outer four
feet. The following graphic shows the four fastening points:
Schematic diagram, system feet
Four transport clamps with two screws each are used to secure the
inspection system to the pallet.

Packing
Packing the inspection system
244
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
Transport clamps
Fastening the
inspection
system to the
pallet
Required: 4 transport clamps with 8 hex head wood screws (10 x 60)
Cordless screwdriver
Perform the following work steps:
1. Set one of the transport clamps around a system foot.
2. Screw down the transport clamp securely to the pallet.
The first transport clamp is fastened.
3. Repeat steps 1 and 2 for the other machine feet, see .„Inspec-
tion system fastening points“ (Page 243)