X7056_Operating manual_en.pdf - 第84页

Installation Integrating th e inspection system into the line 84 Inspection system X7056 | Operating manual | Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a Syst em f ee t Adjusting the he ight of the inspection system R…

100%1 / 280
Installation
Integrating the inspection system into the line
83
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
Line integration: side view
Line integration: top view
Installation
Integrating the inspection system into the line
84
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
System feet
Adjusting the height of the inspection system
Required: 30 mm open-end wrench
Perform the following work steps:
1. Loosen the lock nuts on the system feet.
The feet can now be turned in or out by their lower bolts.
2. Place a PCB in the inspection system transport track.
3. Place the second PCB in the production line conveyor.
4. Slide the PCBs toward each other until they almost touch at the
transition between system and production line (see illustration).
The edges of the PCBs are parallel to each other.
Lock nut
Screw
Installation
Integrating the inspection system into the line
85
Inspection system X7056 | Operating manual |
Version 3.1 Rev.006| 2016-01-06 | 30.009.1930a
5. Adjust the height of the inspection system by tuning its feet in
or out.
The PCBs are on the same height.
The height of the inspection system is adjusted.
Leveling the inspection system to horizontal
Precondition: The inspection system is properly set in place, see „Setting the
inspection system“ (Page 69).
Required: Two PCBs
Two 30mm open end wrench
Carpenter's level
NOTICE
It is also possible to work with two levels at the same time. Set
one level on the x-axis and the other on the y-axis of the posi-
tioning unit and level the system.
WARNING
Hazard of injury
The positioning unit contains strong permanent magnets.
Be careful with the level near the permanent magnets when
leveling the system.
Make sure that the level does not come in contact with the
permanent magnets.
Perform the following work steps:
1. Open the front lift door.
The system interior is open.
2. Set the level on the x-axis of the positioning unit (AOI X).
3. Set the inspection system in a horizontal position as indicated
by the level by turning in or out the housing feet.
The level indicates whether the system is horizontally level.
4. Set the level on the y-axis of the positioning unit (AXI Y).
5. Set the inspection system in a horizontal position as indicated
by the level by turning in or out the housing feet.
The level indicates whether the system is horizontally level.
6. If necessary, repeat steps 2 to 5, until the system is horizon-
tally levelled.