10 Inhaltsverzeichnis 13.1 Most Important Factor fo r Keeping the Line Running 141 13.2 Line Downtime 142 13.3 Important Factors for Keeping th e Line Running 142 13.4 DPM,MFR, Scrap Ra te 144 14 703-Refilling Feeders 14…

Operator Guide SIPLACE Operation of X and SX-Series with SSC
Inhaltsverzeichnis
9
10.3 Important Factors for Prepare the Line 125
10.4 Reject Rate 126
11 703-GUI Overview 127
11.1 PCB Information 127
11.2 PCB being Processed - Running Mode 128
11.3 Light Towers 129
12 Refilling Component Reels 131
12.1 Checking the Component Reels 131
12.2 Splicing - Required Tools and Materials 132
12.3 Preparation of carrier tape end 133
12.4 Preparation of new carrier tape 134
12.5 Splicing the carrier tape 135
12.6 Splicing the carrier tape 136
12.7 Splicing of wide carrier tapes 137
12.8 Checking the splice 138
12.9 After Splicing 139
12.10 Cleaning Tasks 140
13 703 Running the line – Important Factors 141

10
Inhaltsverzeichnis
13.1 Most Important Factor for Keeping the Line Running 141
13.2 Line Downtime 142
13.3 Important Factors for Keeping the Line Running 142
13.4 DPM,MFR, Scrap Rate 144
14 703-Refilling Feeders 145
14.1 Refilling Feeders 145
14.2 Refilling Feeder 146
14.3 Refill Completed 147
15 Option 703 MTC Refill 149
15.1 Refilling MTC 149
15.2 Refill the MTC 150
15.3 Refill the MTC 151
15.4 Loading the new tray. 152
15.5 Refill the Trays 153
15.6 MTC Refill Completed 154
16 Option 703 WPC refill 155
16.1 Refilling the WPC 155
16.2 Refilling the WPC 156

Operator Guide SIPLACE Operation of X and SX-Series with SSC
Inhaltsverzeichnis
11
16.3 Refilling the WPC 157
16.4 Refilling the WPC. 158
16.5 WPC fill completed. 159
16.6 WPC fill completed. 160
17 703-Handling Messages 161
17.1 GUI Messages 161
17.2 Messages - Current 162
17.3 Message Detail 163
17.4 Messages - Statistics 164
17.5 Messages – Statistics – Location 1 165
18 Weekly PM (70x) 167
18.1 Preparations for Maintenance – Materials 167
18.2 Preparations for Maintenance – block the Line 168
18.3 Preparations for Maintenance – stop production. 169
18.4 Preparations for Maintenance – vacuum test 170
18.5 Preparations for Maintenance – vacuum test 171
18.6 Head vacuum test 172
18.7 Head vacuum test - graph 173
18.8 Return the nozzles to the nozzle changer 174