Maintenance Adjustment Main Body Beam This section describes the procedures for adjusting the clearance between the cutter blades. ・ Tools Feeler gauge Allen key 4 mm Hammer ・ Jig FM-1044 Cutter blade installing jig 4-1-…

Maintenance Adjustment Main Body Beam
EJM8A-E-SMA040111-A01-00
Page4-1-11-3

Maintenance Adjustment Main Body Beam
This section describes the procedures for adjusting the clearance between the cutter blades.
・Tools
Feeler gauge
Allen key 4 mm
Hammer
・Jig
FM-1044
Cutter blade installing jig
4-1-12 Adjusting the Clearance between the Cutter Blades
Danger! Do not touch the cutter blades.
Be very careful when removing the cutter unit; it is heavy.
Assembly
Adjustment
45min.
Teaching
min.
Total Time Weight of
Part
Removal
Disassembly
45min.
90min.
40kgs
Caution
Dange
r
Warning
EJM8A-E-SMA040112-A01-00
Page 4-1-12-1

Maintenance Adjustment Main Body Beam
Remarks
Remove the cutter unit.
See "Cutter Unit Replacement." Section 5-9-4
Check the clearance between the fixed and the movable cutter blades.
Record the current clearance.
Feeler gauge
Loosen the screws holding the fixed blade block
Allen key 4 mm
Screw M5 12 pcs.
Raising the fixed blade block, lightly tighten the screws.
Allen key 4 mm
Screw M5 9 pcs.
3
4
1
Item
2
Raise
Tighten lightly
EJM8A-E-SMA040112-A01-00