IT Feeder Manual-45Series(English V2.0)Ver5 - 第73页
Specifications And T echnic al Drawing & PartList Chapter 4. S pecifications And T echnical Drawing & PartList 4.1. Applicable range 4.1.1. Component Placer In the CP40 series and CP45F(V), it only ap plies to ma…

Specifications And Technical Drawing & PartList
Chapter 4. Specifications And Technical
Drawing & PartList
4.1. Applicable range
4.1.1. Component Placer
In the CP40 series and CP45F(V), it only applies to machines that have the IT Feeder
System Option.
4.1.2. Software
Used in the MMI Version 2.500/VME 3.530 and above.
IT Feeder System Version 2.000
Part Station Version 2.000
Feeder Station Version 2.000
4.1.3. Feeder
The Pneumatic IT Tape Feeder With RF-ID TAG can be mounted.
8,12,16,24,32,44,56mm Pneumatic IT Tape Feeder
12, 16, 24, 32, 44, 56mm Pneumatic IT NST Feeder
4.2. Configurations
4.2.1. Mechanical Part
Feeder Base: It is where the Feeder is mounted.
RF-ID Driving: It move the ID Scan Device Using the Step Motor and Timing Belt.
Switch: It consist of Ball and Switch Pin. It let the Switch Board know if the IT
Feeder is mounted or not.
4.2.2. Control Part
Antena Board: It scan the RF-ID TAG attached to IT Feeder.
Reader Board: Transmits data between the Antena Board and the IT CPU Board
installed in the equipment.
Switch Board: Checks whether a feeder is installed in each slot of the Feeder Base.
Flat Cable: Cable for data transmission between the Antena Board and the Reader
Board.
Cart Ext Cable: Cable for data transmission between the IT Feeder Base and the IT
CPU Board installed in the equipment.
4-1

Samsung Intelligent Feeder System
4.3. Inspection and maintenance
4.3.1. Inspection Method
Preparation (IT Feeder Ass’y)
Connect the Cable connector of IQ Feeder Jig to the RF-ID Reader, and connect
the Cable connector of the RF-ID Reader to the RS232 Port of the computer.
Supply power (AC220V) and turn on the Power.
Run the IQ Feeder inspection program in the computer.
Prepare the IQ Feeder to be inspected in the IQ Feeder Jig.
Preparation (IT Feeder Base Ass’y)
Connect the cable between the IQ system controller and the RS232 port of the
computer and supply power(AC220V).
Run the IQ Feeder Base inspection program in the computer.
Connect the Car Ext Cable of the IT Feeder Base Ass’y to be inspected to the IT
Feeder Base1 connector of the IT Feeder System Controller.
Inspection (IT Feeder Ass’y)
Install the IQ Feeder to be inspected in the IT Feeder Jig.
Click on the ID Reader button in the PC.
Check whether the ID number is displayed on the screen.
Inspection (IT Feeder Base Ass’y)
Install the Master ID Feeder in the slots 1 - 6.
Check if the feeders installed in the slots 1 - 6 are identified by colors on the PC
monitor (The slot showing no color change is defective and the switch is not
working properly).
Check if the IDs installed in the slots 1,2,3,4,5, and 6 are identified by numbers
on the monitor. (Check if there are any duplicated IDs or missing IDs. These are
defective.)
Install the Master ID Feeder to the slots 7~12 and repeat the second and third
procedures.
Repeat the procedures to check all 48 slots.
4.3.2. Maintenance
Here only the most important matters that might cause functional difficulties are
described and other precautions for handling are the same as those for general ASS’Ys.
Take extra precautions so that chips or other contaminants are not left between the ball
and bush that works as the switch, and clean up the surface of the feeder base with air
before installing the feeder. Be sure not to exert any undue impact on the area where the
RF-ID is to be attached.
4-2