4 Setting up and commissioning 4.2 Configuration when delivered 36 User Manual SIPLACE Nozzle Cleaning Station 09/2019 4.2 Configuration when delivered 4.2.1 Services As a special service, SIPLACE offers to realize the c…

4 Setting up and commissioning
4.1 Safety instruction for transportation
User Manual SIPLACE Nozzle Cleaning Station 09/2019 35
Fig.17: Machine support points / Machine/component handling
Move the machine on its wheels when
handling. Lift the machine with forklift
trucks with a minimum capacity of 500
kg and load the machine onto the forks
400 mm away from the fork carriage. Di-
mensions and fork entry points (marked
"P") - (see fig.).
The warehousing and storing of this
machine require an indoor room. Pro-
tect the machine from dust and keep its
electrical components dry. Before mov-
ing to storage, thoroughly clean the
machine of processing residues.

4 Setting up and commissioning
4.2 Configuration when delivered
36 User Manual SIPLACE Nozzle Cleaning Station 09/2019
4.2 Configuration when delivered
4.2.1 Services
As a special service, SIPLACE offers to realize the complete integration of your nozzle cleaning
station in your facility. With our extensive expertise and by using the right tools and equipment, we
can ensure that the installation process runs smoothly and efficiently. However, this will require you
to clarify the infrastructure aspects in advance and make any necessary changes at your produc-
tion facility.
4.2.2 Shipping packaging
The SIPLACE NCS and cleaning options are delivered in separate packages. The NCS is packed
in a wooden crate and the cleaning options are packed in cardboard with foam inlays.
CAUTION
Damage from condensation
To avoid damage from condensation, only open the packaging once the NCS or the com-
ponents have adjusted to the ambient temperatures. This can take up to 24 hours.
4.2.3 Checking a delivery
► Check the delivery for damage.
► Unpack the machine and the accessories and check the delivery for completeness (reference
delivery note).
► Document the results in the installation report /acceptance protocol.
4.2.4 Shipping braces
Fig.18: Transportation crate/pallet - shipping braces
The SIPLACE NCS gets delivered seated on
two wooden bars. In addition, a wooden
bracket is screwed to each side to prevent it
slipping.

4 Setting up and commissioning
4.2 Configuration when delivered
User Manual SIPLACE Nozzle Cleaning Station 09/2019 37
4.2.5 Transporting the placement machine in the shipping crate or on the pallet
Fig.19: Transportation crate/pallet - attachment points for
transportation with the fork-lift
The transport crate or pallet should only be
lifted at the side.
► Transport the SIPLACE NCS on the
pallet / the crate as near as possible to
the final site of use.
4.2.5.1 Shipping packaging dimensions
The dimensions of the pallets and wooden crates are listed in the following table:
Machine (L x W x H)
Pallet 1410 mm x 1210 mm
Wooden crate 1500 mm x 1300 mm x 2200
4.2.5.2 Weight of machine when ready for dispatch
The following table contains the weights of the placement machines prepared for dispatch, includ-
ing packaging.
Machine Dispatch
SIPLACE NCS 350 kg
4.2.5.3 Transportation equipment for transporting the placement machine in the packaging
Use a pallet truck / fork-lift truck with the following specification to carry the placement machine:
Machine Dispatch
Fork length Min. 1200 mm
Lifting power Min. 500 kg