Retrofit instructions Short Sleeve 05/2004 Edition 26 4.3.2 Chan ge of setup / STOP Production 4 4 Production STOP Last PCB placed? Further p lacement YES NO STOP of st at io n whe r e hig h c omp onen ts we re p lac ed …

100%1 / 28
Retrofit instructions Short Sleeve
05/2004 Edition
25
4.3 Placement of high components
4.3.1 Job schedule / START Production
4
Production START
Job at
the station ?
Job schedule from LCU
YES
NO
Station collecting nozzles automatically
Stop station
Changing manually to single functions / Nozzle configuration
Change dedicated nozzle by using start step function
The special nozzle for the high component is assigned
in the setup/nozzle changer.
Status: Stand. Segment with standard nozzles are o
n the specific RV head.
Manual change of sleeves and nozzles
Starting manually vacuum- and height reference run
Release station for standard production
YES
Retrofit instructions Short Sleeve
05/2004 Edition
26
4.3.2 Change of setup / STOP Production
4
4
Production STOP
Last PCB
placed?
Further placement
YES
NO
STOP
of station where high components were placed
Changing manually to single functions /
nozzle configuration
Change dedicated nozzle by using start step function
Starting manually vacuum- and height reference run
Reset the
current job on the line computer
Scheduling
following job
Automatically
all nozzles were changed
Automatically
all reference runs are done
Production
of following product