1. Overview
This chapter explains typical daily operation per the flow chart shown below.
Start YSi-V
Pre-operation inspection
Warm-up operation
Change inspection program
Change conveyor unit setup
Inspect same board as previous time?
End inspection
Start inspection
(automatic inspection)
Turn power off
Daily operation flow
YES
NO
Select board
23300-M9-00
3-2
3
Daily operation
2. Warm-up operation
After starting the YSi-V, perform warm-up (aging operation) of servo motor axes.
n
NOTE
A warm-up period of 15 minutes is sufficient.
Note that no warm-up operation is necessary if less than 2 hours have elapsed since the last operation.
1
Carry out the pre-operation check before starting the YSi-V.
For pre-operation checks and starting up the YSi-V, see "Chapter 2 Basic operation".
2
Start warm-up operation.
c
CAUTION
Check that there are no boards on the conveyor before beginning warm-up. If push-up pins are used, remove them.
If a problem occurs during warm-up, press the [Stop] button to stop the operation. Then check the cause of the
problem and eliminate it.
1. Press the [Warm-up] button to open the warm-up screen.
2. Press the [Start] button to start warm-up operation.
"Setup" screen
Warm-up
2
24300-M9-10
n
NOTE
If you want to specify the warm-up time, press the [Stop after time-over] button and enter the desired warm-up time.
3
End the warm-up operation.
Press the [Stop] button to end the warm-up operation. In most cases, a warm-up period of 15 minutes is
sufficient.
4
Press the [Close] button to return to the operation screen.
3-3
3
Daily operation
3. Selecting a board
Select the board to be inspected from the list of created programs.
1
In the inspection program list, select the board to be inspected.
Press the [Select] button to read out the board in the list or directly double-click on the corresponding
row in the list to load the inspection program.
c
CAUTION
When the inspection program is loaded, the conveyor width will be automatically adjusted to the board width (board
size Y). Remove the push-up pins before selecting the board.
Selecting board
Select board.Name of inspection program loaded Image of board
[Select] button
24301-M9-10
2
Check the loaded inspection program.
The name of the loaded inspection program appears in the status area. Check that this particular name
agrees with the name of the selected board.