00191332-01.pdf - 第160页

4 Mapping User Manual Test Program SITEST 4.3 RV Mapping Software Version 405.xx Issue 01/99 4 - 12 ● If a dua l conve yor is install ed, acti v ate th e radio button for the conve yor track f o r which ma pping is to be…

100%1 / 168
User Manual Test Program SITEST 4 Mapping
Software Version 405.xx Issue 01/99 4.3 RV Mapping
4 - 11
4.3.1 Mapping Run for Both Gantries (SIPLACE 80S-20/S-23)
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping is to be
performed.
Click on the
Start
button in the "RV mapping both gantries" field and follow the directions displayed on
the screen.
The mapping run is performed for gantry 1. After the mapping run, gantry 1 is automatically moved to
the park position and subsequently the mapping run for gantry 2 is performed.
After the mapping run has been completed without any errors, the data thus determined is automatically
saved.
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping has not
yet been performed.
Click on the
Start
button in the "RV mapping both gantries" and follow the directions displayed on the
screen.
The mapping run is performed for both gantries on the selected conveyor track.
After the mapping run has been completed without any errors, the data thus determined is automatically
saved.
Click on the icon to return to the main view.
4.3.1.1 Mapping Run for the Active Gantry
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping is to be
performed.
Click on the
Start
button in the "RV mapping of selected gantry" field and follow the directions displayed
on the screen.
The active gantry now performs the mapping run. After the mapping run has been completed without any
errors, the data thus determined is automatically saved.
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping has not
yet been performed.
Click again on the
Start
button in the "RV mapping of selected gantry" field and follow the directions
displayed on the screen.
The active gantry performs the mapping run on the selected conveyor track. After the mapping run has
been completed without any errors, the data thus determined is automatically saved.
Click on the icon to return to the main view.
In the main view SIPLACE 80S-20/S-23 click on the icon to switch to the "RV head 2" display.
Click on the icon to switch to the "RV mapping" display.
4 Mapping User Manual Test Program SITEST
4.3 RV Mapping Software Version 405.xx Issue 01/99
4 - 12
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping is to be
performed.
Click on the
Start
button in the "RV mapping of selected gantry" field and follow the directions displayed
on the screen.
Gantry 2 now performs the mapping run.
After the mapping run has been completed without any errors, the data thus determined is automatically
saved.
If a dual conveyor is installed, activate the radio button for the conveyor track for which mapping has not
yet been performed.
Click again on the
Start
button in the "RV mapping of selected gantry" field and follow the directions
displayed on the screen.
Gantry 2 performs the mapping run on the selected conveyor track.
After the mapping run has been completed without any errors, the data thus determined is automatically
saved.
Click on the icon to return to the main view.
NOTE
RV mapping can also be performed using the
Calibrate machine...
-->
Head mapping
function (see chapt. 3,
section 3.2). On SIPLACE 80S-20/S-23 machine types, this function is used to perform automatically the map-
ping procedure, first for gantry 1 and then for gantry 2.
If a dual conveyor is installed on the machine, mapping is performed first on the right and then on the left
conveyor track.
4
CAUTION
As the data will be overwritten during PCB mapping, it is necessary that RV mapping and IC mapping
(SIPLACE 80F
4
/F
5
) be repeated after every PCB mapping operation.
4
User Manual Test Program SITEST 4 Mapping
Software Version 405.xx Issue 01/99 4.4 IC Mapping
4 - 13
4.4 IC Mapping
NOTE
Prior to the performance of IC mapping make sure that PCB mapping has already been carried out.
4
Carry out the preparatory steps as described in section 4.1.
Additional prerequisites are:
Segment offset II (RV-PCB camera offset) must already have been determined.
The calibration tool must be in the calibration tool pocket.
The calibration tool position must already have been determined.
The IC camera must have been completely calibrated.
On the IC head, a type 416 nozzle must be attached.
In the main view SIPLACE 80F
4
/80F
5
click on the icon to switch to the "IC head" display.
Click on the icon to switch to the "IC mapping" display.