Module Function
6-21
6.12. Pneumatic Part
Generally, the air pressure values in the range of 0.45 – 0.55 MPa can be set and used.
The air flows through the main inlet at the rear bottom end of the machine. One portion is
used for operating the multi-cylinder of the feeder station, another portion is used for
driving ANC, still another portion is used for generating vacuum in the head, and the
remaining portion is used for operating stoppers of the conveyor.
Pressure Gauge (View)
Regulator
Coupler (male)
Air Filter & Auto Drainer
Manifol
d
Pressure with
Auto Switch
Figure 6-21. Pneumatic Part Main Inlet
Caution
If the pressure is under the appropriate level, the machine
might operate irregularly.
In general, 0.45~0.55 MPa is appropriate for the air
pressure.
Warning
Failure of disconnecting air pressure and power supply
for the repair and maintenance of machine could result in
severe injury.
Be sure to disconnect air pressure and power supply for
the repair and maintenance of machine.

Transfer & Installation Procedure
Chapter 7. Transfer & Installation
Procedure
7-1
Initial operation of this machine should be performed according to the following
procedure.
Warning
If the machine is installed or test run by an untrained
person, the machine might be damaged and personal
injury could occur.
The installation or test run of machine must be carried out
by our authorized C/S personnel only.
Installation procedure
1. Before heading to the site, the personnel in charge of the installation and test
operation shall confirm the shipment detail with the Production Management
Department, and inform the customer of the expected time of arrival at the site.
2. Following arrival at the site, a visual inspection of the external appearance of the
product (box distortion, etc.) shall be performed prior to unloading the machine.
3. Prior to unloading the machine, be sure to check the safety provisions and if
necessary, install the security fence to ensure safety. (ex: working in a high building)
4. The personnel in charge of the sales department shall: receive the delivery
confirmation and acceptance certificates from the operator; check the condition and
quantity of the machine after it has been unloaded; and, sign the receipt to complete
the take-over procedure with the operator.
5. When unloading the machine, the personnel in charge of the installation and test
operation shall give instructions to the workers from the machine handling company
to be careful that there will not be any damage to the machine caused by a forklift or
crane. He/she shall advise them of precautions in handling the fragile parts before
they unload the machine, and see that they use the proper jig and handling machine.
Unloading work shall be performed using a forklift and crane only.
6. Unpack the package.
Caution
When unpacking the machine, excessive shock may
damage the cover of the machine. Be careful not to apply
excessive force when unpacking the machine.
Before using a crane, the wood on the pallet shall first be
removed by wrench drill. Next, open the box and remove
the plastic cover. At this time, care should be taken not to
scratch the machine.
7. When using a forklift or crane for moving the machine, refer to the following figure
and procedure.