Introduction(CP45FV) Eng.pdf - 第94页

Samsung Component Placer CP45FV Series Intr oduction Figur e 7-2. How to r emove Clamp X Caution If the power switch is turned on without removi ng the X and Y clamps, the machine may become damaged. Remove the X and Y c…

100%1 / 109
Transfer & Installation Procedure
7-3
④ Check the hook locking
device.
③󰚟Sling the rope (check the rope length to
maintain the level of the machine).
②󰚟Insert the steel bar an
d
check its fixing state to
prevent perpendicula
r
leaning)
⑤󰚟 Protect the surface frombeing
scratched (preventing the cove
r
from damage).
Figure 7-1. How to move the machine using a crane
①󰚟Remove hole cup
8. When moving the machine to its final destination after it has been unloaded from the
pallet, it should be moved with all of its legs completely lifted. Be careful not to
break the casters in locations where barriers are located such as cargo elevators. In
principle, a hand lift shall be used to move the machine.
Caution
When the machine is installed on a surface that is made of
wood or shock absorbing material and not rigid enough,
excessive vibration may be generated during the machine
operation. Be sure to install the machine on a rigid surface.
9. Once the machine has arrived at its designation location, the position of a system line
where the machine is installed should be confirmed by the client’s supervisor. Then,
install the machine by moving it in left and right directions based on the position of
the machine where the tray feeder is installed.
10. In the case of in-line installation, the legs shall be adjusted so that they may be
aligned with the height of conveyors on the pre-process machine and after-process
machine. Before performing height adjustment, remove the front and rear covers of
the machine.
11. Remove the X clamps fixing the ball screws of the X axis (including the urethane
cushion).
Samsung Component Placer CP45FV Series Introduction
Figure 7-2. How to remove Clamp X
Caution
If the power switch is turned on without removing the X and
Y clamps, the machine may become damaged. Remove the
X and Y clamps before supplying power.
12. Remove the Y clamps fixing the ball screws of the Y axis (including the urethane
cushion).
Figure 7-3. How to remove Clamp Y
13. If necessary, remove the cable ties bound on the Z axis, and move the head manually
to the center. Also, keep the clamps in the plastic bag after fixing it with screws.
Caution
It may cause damage to the machine if the machine is
operated without removing the cable ties bound on the Z
axis. Be sure to turn the power on after removing the cable
ties bound on the Z axis.
14. The reference level of the machine is EL+900mm and 950mm (based on Europe
standard, CE) from the surface of the PCB, that is, the surface of the conveyor.
However, depending on the floor condition (slope), ±15mm is allowable.
7-4
Transfer & Installation Procedure
7-5
Level
Figure 7-4. Machine level adjustment – using the spanner supplied with the machine
15. Adjust the level placing the level on the top surface of the feeder base and Y1 axis
L/M guide. The accuracy of the level gauge shall be 0.02mm/m, and its tolerance
shall be less than 0.05mm/m.
16. The foot of the machine must be supported on the floor with even supporting force.
To achieve this, the locking pressure of the nuts of the leg shall be adjusted so that
equal force may be applied to the legs. Check if there is any nut loosely tightened.
After level adjustment is completed, tighten the nuts securely.
Caution
Unless the machine is level, the accuracy of the machine
will be affected. Ensure that the machine is level and check
if the legs of the machine are tightened securely.
The procedure for adjusting the level of the machine is given below.
After moving the new machine near to the existing one, lower the legs of the machine
so that it is aligned level with the existing machine. Then adjust the level keeping the
level difference below 0.1mm/m.
Using a lever, move the machine to the position where the gap between the existing
machine and the edge of the conveyor can be kept between 3~5mm.
Put the PCBs on each conveyor of the two machines, and set the machines so that the
level difference is 0.05~0.1mm, enough to allow the PCBs to move downward.
Essentially, the slope of the conveyor shall be set to allow for the “Downflow” of the
PCB in the direction in which the PCB is moving. To ensure the straight movement of
the PCB between machines, the machines must be installed correctly so that there
will be no unparallel gap at either front or rear side of the PCB, when the PCB is
tightly contacted to the reference line.