4 Setting up and commissioning 4.3 Setting up the machine 60 Instruction Guide ASM ProcessLens 02/2017 4.3 Setting up the machine 4.3.1 Warning instructions DANGER Only ASM SMT Solutions engineers or qualified people are…

4 Setting up and commissioning
4.2 Infrastructure at the installation location
Instruction Guide ASM ProcessLens 02/2017 59
4.2.2.3 Mains connection - delivery configuration
The main power connection is configured according to the power supply of the country concerned.
●
The machine is configured for 110V AC (optional) to 240V AC voltage.
The machine has a mains power cord AWG 14, 300/500V 3 x 2.5 mm² WITHOUT plug.
Fig.36: Description of wires in the mains power cable
1 brown = (L1): phase 2 blue = (N): neutral conductor
3 green/yellow = (PE): conductor
-or-
●
The machine is configured for 110 V AC (optional) to 240V AC voltage.
The machine has a mains power cord AWG 14, 300/500V 3 x 2.5 mm² WITH C form plug.
Fig.37: Assignment in the C form plug

4 Setting up and commissioning
4.3 Setting up the machine
60 Instruction Guide ASM ProcessLens 02/2017
4.3 Setting up the machine
4.3.1 Warning instructions
DANGER
Only ASM SMT Solutions engineers or qualified people are permitted to set up and
commission the machine
► Always follow the applicable accident prevention regulations.
► If you still need to perform assembly work to the underside of the machine, take
appropriate measures to secure the machine first. The forklift must not be used as the
only support.
► Make sure that the inspection head is positioned over the PCB conveyor area so that
you do not restrict your head movement during assembly, thus excluding the risk of in-
jury.
► Two people will be needed to adjust the height of the machine:
► One person to carry out the necessary assembly work and the other person to watch
the raised machine during assembly and ensure that it does not move.
► Wear special safety boots to protect your feet.

4 Setting up and commissioning
4.3 Setting up the machine
Instruction Guide ASM ProcessLens 02/2017 61
4.3.2 Lifting and transporting the machine with the forklift truck
Fig.38: Contact surfaces - forks parallel to the direction of PCB transport
1 Contact surface for forklift truck forks
► Position the forklift truck at right angles to the PCB conveyor and open the forks until the con-
tact surfaces of the machine lie evenly on the forks.