JaNets Instr ucti on Man ual 8. Job Optim izer 8- 55 When any error is found while che cking data c oher ence, t he “ Data Coheren ce Check Re sults ” tab is displaye d. Also, you can select the “ Data Co herence Ch eck …

100%1 / 755
JaNets Instruction Manual 8. Job Optimizer
8-54
Data Coherence Check
This command allows you to perform the coherence check for the data you created.
Figure 8.3-92 Main screen [Optimize] - [Data Coherence Check]
The system starts the data coherence check, and the Data Coherence Checkdialog box appears
on the screen.
Figure 8.3-93Checking data coherence” dialog box
Select the [Optimize]
command, and then the [Data
Coherence Check] command
on the Optimizemenu, or
click the Data Coherence
Checktool ( ) from the
toolbar.
When the Data Coherence Check normally
finishes: The message indicating that the Data
Coherence Check finishes appears on the screen.
JaNets Instruction Manual 8. Job Optimizer
8-55
When any error is found while checking data coherence, the Data Coherence Check Results
tab is displayed. Also, you can select the Data Coherence Check Resultscommand from the
Viewcommend.
Figure 8.3-94 [View] [Data Coherence Check Results]
Figure 8.3-95 Main screen Detailed data display area: Data Coherence Check Results
* When the "Saving the state at the time of an exit" is set to the "No in the environment setting of
the Program Editor, you start the Program Editor in the state of new creation. When you start
the Program Editor from the Job Optimizer, make sure that the "Saving the state at the time of
an exit" is set to the “Yes” in the environment setting of the Program Editor.
For the environment setting of the program editor, refer to “7-6-6-2 Environment setting.
If the Data Coherence Check detects
an error, the Data Coherence Check
Error” message appears on the
screen. In this case, you can select the
[Data Coherence Check Results]
command from the Viewmenu.
The Data Coherence
Check Resultstab
appears on the Detailed
data display area of the
Main screen.
Select one line, and click the <View in Program Editor> button, or double-click one line. The Program
Editor starts up. A production program selected with the Program Editor opens, and the error list
appears on the screen.
JaNets Instruction Manual 8. Job Optimizer
8-56
Time Estimate
Figure 8.3-96 [Optimize] [Time Estimate] Figure 8.3-97Time Estimatedialog box
When the user operation time zone is not set yet, the message indicating the operation time zone
is not set yet appears on the screen, and you cannot execute the Time Estimate function. In such
a case, set the user operation time zone on theCalendartab of the Set Environmentsdialog
box invoked from the Shop Floor Setup.
When the optimization is not executed or the production program is changed after the optimization,
the time estimate cannot be selected.
When the Planned Start Date and Planned Start Timeare set for a reservation file to which you
are to execute the Time Estimate function, the system displays the date and time as the Start
Date and Timeon the Time Estimatedialog box.
Figure 8.3-98Simulatingdialog box
After simulation, the Estimated Timedialog box appears on the screen.
Figure 8.3-99Estimated Timedialog box
Time Required: Simulation results + Changeover time
Update: This button displays the message that asks you whether
to change the data of the reservation list. When you click the
<Update> button, the items Planned Start Date,” “Planned Start
Time,” “Planed End Date and Planned End Timeof all
production programs are updated.
Start: Starts the tact simulation.