JANETS_INM - 第531页

JaNets Instr ucti on Man ual 13 . Program D ownloa der 13 - 35 13.9.11.2 Specifying a program to be added (when t he D ata Manager is no t used) Select a progr am to be ad ded on the d ialog box for specifyi ng a file. Y…

100%1 / 755
JaNets Instruction Manual 13. Program Downloader
13-34
13.9.11 Interruption production
This is a function for adding a production program not planned to the Production schedule list.
You can add a program to production either according to a production program or a reservation
file.
13.9.11.1 Calling the function
Select a program located at a positon to which you want to add another program among programs
displayed in the Production schedule list, and click the right button of the mouse. The menu
including the command [Add a production program] appears on the screen. Next, select the
positon to which you want to add a program on the submenu. Select the command [Add above
this program] to add a program above the selected program. Select the command [Add below
this program] to add a program below the selected program.
Figure 13.9-29 Calling the function for adding a production program
When you select the menu command [Add above this program] or [Add below this program], you
are supposed to specify a file to be added. The operation varies depending on whether you use
the Data Manager or not. If you cannot add any program to the selected position, the menu is
disactivated. The conditions under which any program cannot be added are described below.
[1] If all programs displayed in the Production schedule list finished the corresponding
productions, you cannot add any program.
[2] When you select the first program in the Production schedule list, you cannot select the
command [Add above this program].
[3] You cannot add any program between two programs whose productions have finished.
[4] If there is data to which “Cluster teaching” is specified in a reservation file, any program
cannot be added to the reservation file regardless of whether you will perform teaching
operation or not.
JaNets Instruction Manual 13. Program Downloader
13-35
13.9.11.2 Specifying a program to be added (when the Data Manager is not used)
Select a program to be added on the dialog box for specifying a file. You cannot specify two or
more programs.
13.9.11.3 Specifying a program to be added (when the Data Manager is used)
When you use the Data Manager, the screen for specifying a program selection method appears:
select a program from a folder of the JaNets PC or select a program among those displayed with
the Program Explorer.
Figure 13.9-30 Screen for selecting a place where a program to be added is saved
When you click the <Folder> button
Select a program to be added on the dialog box for specifying a file in the same manner as
when the Data Manager is not used.
When you click the <Program Explorer> button
Programs displayed with the Program Explorer are displayed in a tree list form. Note that a
program not specified for an active display production line or a program checked out by
another user who has logged in the system is excluded.
JaNets Instruction Manual 13. Program Downloader
13-36
Figure 13.9-31 “Specify a production program” screen
Select a program to be added among those displayed in the list, and then click the <OK> button.
You cannot select two or more programs. If the selected program is not checked out yet, it is
checked out before a production program is loaded to the system. When you click the <Cancel>
button, specification of the program is cancelled, and the screen is switched back to the screen for
selecting a place where a program to be added is saved.
13.9.11.4 Loading a program to be added
Load a program you want to add. The system checks an active display production line, the line
configuration and whether optimization has been conducted already. If any error occurs due to
one of these checks, the program addition processing is aborted.
Check of the active display production line
If the production line for the selected production program is different from the active display
production line of the Program Downloader, the error message shown below appears on the
screen.
Figure 13.9-32 If a production line specified with a production program is different
from the active display production line