User Manual SIPLACE D3 4 Setting up and commissioning From software version SR.605.xx 07/2008 EN Edition 4.6 Commissioning the machine 251 4.6.3 A test run or st arting production → T est the line using the test PCB or a…

4 Setting up and commissioning User Manual SIPLACE D3
4.6 Commissioning the machine From software version SR.605.xx 07/2008 EN Edition
250
→ Wait until the operating pressure for the tape cutter has dropped to 0 MPa.
→ Wear robust protective gloves.
→ Do not reach inside the used tape channel.
4.5.2 Removing the separating plate
→ Loosen the two slotted screws (item 4 in Fig. 4.5 - 1, page 249)
→ Pull out the dividing plate.
4.6 Commissioning the machine
4.6.1 Commissioning the machine at the customer's premises
→ Check all modules for correct seating.
→ Wipe off the linear guide rails with a lint-free cloth before removing the shipping braces for the
X/Y axis. Do not use any solvent to do this (see Section 4.3.20
, page 245.
→ Switch on the machine and perform a reference run.
→ Copy the placement program onto the computer and test it.
→ Check the machine zero point after a period of warming up of 3 - 4 h.
→ Get the customer's operating personnel to equip the feeder modules according to the cus-
tomer's placement program.
→ Instruct them in handling the feeder modules using the JobGuide.
→ Check all customer-specific installed options (in particular software) for good functioning and
order any necessary spare parts using the order form or by fax.
4.6.2 Instructing the customer's personnel
→ Explain all customer-specific installed options, in particular software / software compatibility.
→ Explain programming of the program editors on the line computer / SIPLACE Pro.
→ Instruct the operators and line engineers in using the station software.
→ Explain about password protection.
→ Instruct the customer's personnel according to the user manual and preventive maintenance
manual.
User Manual SIPLACE D3 4 Setting up and commissioning
From software version SR.605.xx 07/2008 EN Edition 4.6 Commissioning the machine
251
4.6.3 A test run or starting production
→ Test the line using the test PCB or a PCB provided by the customer.
→ Record the customer product and performance data, prepare the data and document the data
in the installation report.
→ Secure the data and give the customer security copies.
4 Setting up and commissioning User Manual SIPLACE D3
4.6 Commissioning the machine From software version SR.605.xx 07/2008 EN Edition
252