4 Camera Calibration in Stations from SW705.03 4.3 FCCS in Placement Line as of SW 707.xx 66 Operating Manual / Bedienungsanleitung Camera Calibration FCCS digital Kamerakalibrierung FCCS digital 04/2020 From SW 705 Fig.…

100%1 / 86
4 Camera Calibration in Stations from SW705.03
4.1 Camera calibration from station software 709.0 und 712.1
Operating Manual / Bedienungsanleitung Camera Calibration FCCS digital Kamerakalibrierung FCCS digital 04/2020 65
4 Camera Calibration in Stations from
SW705.03
NOTICE
For report purposes you can find two XML files for each camera in C:\SR-Daten
\FCCS.
The file names have a time stamp and the following identifiers:
- gantry name
- camera type name
- before / after calibration
- date stamp
Example: Gantry_1_CameraID_25_after_FCCS_2008_06_06_14_01_28.xml
NOTICE
From SW709.0
On the station computer: C:\Sirio\Work\MaintenanceReports
On the SIPLACE Pro computer: C:\MaintenanceReports
4.1 Camera calibration from station software 709.0 und 712.1
The maintenance GUI was introduced with station software 709.0 and the function "Calibrating illu-
mination" (now "Camera verification") was moved there.
In addition, the camera check has been extended to include the function "Check camera for soiling"
from station software 712.1. This function extension can be performed separately or as a precursor
to the camera check. See also 4.5 "Calibration sequence in SW 7xx.xx" [}69]
4.2 Preparations
NOTICE
Dry run
To ensure the successful camera calibration for the complete line, it is recommended to
perform a dry run of the camera calibration without saving the calibration values.
This is necessary, because aborting the calibration will lead to different illumination values
of the cameras in the line. The reliable detection of components throughout the whole line
cannot be ensured until the camera in question has been replaced and all cameras in the
line have been re-calibrated.
To ensure that customer setups do not need to be changed, a black calibration tool carrier is
moved into PCB conveyor 1, is optically centered and clamped into place, the presence of the
white balance calibration tools is checked and illumination calibration (white balance process) is
started.
NOTICE
Pre-requisites: nozzle configuration, conveyor width etc.
You can leave the SW wizard at any time in order to pick up the required nozzle types via
the single menus.
4 Camera Calibration in Stations from SW705.03
4.3 FCCS in Placement Line as of SW 707.xx
66 Operating Manual / Bedienungsanleitung Camera Calibration FCCS digital Kamerakalibrierung FCCS digital 04/2020
From SW 705
Fig.21: Calibrate illumination
Switch on the machine.
Press the Start button to start the overall
reference run.
Log in as Service (customer).
Switch over to the SERVICE menu.
Select Calibrate illumination.
See also …
4.7 "Report File from SW 705.03 onwards" [}72]
From SW 709
Fig.22: GStart overall reference run
Switch on the machine.
Press the Start button to start the overall
reference run.
Log in as Service (customer).
Fig.23: Camera verification
Switch over to the Maintenance menu.
Select Camera verification.
4.3 FCCS in Placement Line as of SW 707.xx
Due to the fact that the conveyor area in machine types as of SIPLACE SX1/2 is difficult to access,
the following function has been integrated in the station software as of the 707.0 version.
4 Camera Calibration in Stations from SW705.03
4.4 FCCS in placement line from SW 709.xx
Operating Manual / Bedienungsanleitung Camera Calibration FCCS digital Kamerakalibrierung FCCS digital 04/2020 67
FCCS measurement in the placement line
The tray with the white standards shall be transported through those placement stations at which
no FCCS measurement is to be performed.
Fig.24: Calibrate illumination
At these machines, switch over to the Ser-
vice view => Calibrate illumination, to
ensure pass-through.
Fig.25: Select cameras at the machine
Only select cameras on the machine at
which you want to perform the measure-
ment by clicking on the respective check
box and entering a tick in it. (For the ma-
chines of the stations at which you do not
want to perform measurements, i.e. the
tray will only be passed through, you do
not need to select these machines.)
Click on Next.
ð The dialog "Ensure preconditions are
fulfilled before continuing" is displayed
(as in the case of the other stations).
Fig.26: Start
Click on Start.
ð The tray moving in will now be directly
transported through the machine as no
camera has been selected for measure-
ment.
4.4 FCCS in placement line from SW 709.xx
Checking as part of the camera verification (FCCS)
The function "Check for camera soiling" (from SW 712.1) was also integrated into the "Camera
verification (FCCS)" function and is always performed before the actual camera verification.