00195963-03_MM SWS-EN - 第39页

39 . ► ► Screw th e grub scr ew [4] into th e threade d hole prov ided [3] and fix the sealing u nit into place (tig hten with care) . Finally C omplete t he die ejecto r. NOTICE Old needle ejector unit with bayonet fa s…

100%1 / 79
:
Pull the sealing unit up and out.
If it is not possible to pull the sealing unit out, clamp a small Allen key into the sealing
unit drilled hole and try to pull it up.
It should then be possible to remove the sealing unit.
Take the new compete sealing unit and grease the O-ring with UNISILCON L250L (thin
layer of lubricant).
Place the new sealing unit incl. O-ring into place and push down as far as the stop
39
.
Screw the grub screw [4] into the threaded hole provided [3] and fix the sealing unit into
place (tighten with care).
Finally Complete the die ejector.
NOTICE
Old needle ejector unit with bayonet fastening
If the side Allen screw on the centering unit is difficult to access, you may need to
remove the four screws fastening the lock ring and remove this ring.
Place the lock ring back and fix into place, before tightening the Allen screw on the
side.
Lubricating the Shaft for the Z Movement at the Needle System
Interval: 4 months
Equipment: Spray grease (aerosol)
The shaft for the Z movement (ejection) must be easily movable by hand in its bronze guide and
should therefore be lubricated regularly.
Legend
[1] Lubrication point
Slightly move the Z shaft out of its bronze guide.
Spray a bit of spray grease on the lubrication points shown [1].