3-2 3 Starting and ending pr oduction n NOTE When producing boards using both lanes of dual-lane machines, use the [ Lane select ] button to select the lane to be operated and then adjust or check the conveyor unit setup…

3-1
3
Starting and ending production
1. Starting production
This section describes how to select the board data which is already registered and perform component
mounting.
1
Select the board data.
1. When the board data is not yet selected, press the [Board] button on the Setup screen.
A list of registered board data appears.
In dual-lane machines, the lane select button is displayed on the "Board data select" screen, so press
that button to display the lane to be used for production. (When producing boards using both lanes,
select "Lane combination".)
2. Line up the cursor with the board data to use for production and press the [Select] button.
The machine loads the seleted board data.
Selecting the board data
Select board data from list.
Press [Board] button.
Lane select
button.
Selected board name is displayed.
24300-L4-10
TIP
• Combined board data will be displayed when "Lane combination" is selected with the lane select button.
Combined board data includes two board data which are stored in one board file. Combined board data is
displayed along with an orange icon.
• When combined board data is selected, the board le name and board data name used for production on the
selected lane are displayed on the Setup screen.

3-2
3
Starting and ending production
n
NOTE
When producing boards using both lanes of dual-lane machines, use the [ Lane select ] button to select the lane to
be operated and then adjust or check the conveyor unit setup.
2
Set up the conveyor unit.
Open the [Unit] - [Conveyor] tab screen, and adjust the conveyor width and push-up pins according to
the board. For further details, refer to "3.4 Adjusting the convey unit setup" in Chapter 2.
[Unit] − [Conveyor] screen
Example of Dual-lane
24301-L4-10
3
Check the other setup items.
Return to the [Setup] screen, and press the following buttons to check or change the setting data.
3
124
Setup screen
Example of Dual-lane
24302-L4-20
1. [Required Parts] button
Displays the designated feeder set positions and components to be mounted. Check whether the necessary feeders are
installed in the correct feeder set positions on the feeder plate.

3-3
3
Starting and ending production
2. [Required Nozzles] button
Displays a list of nozzle types that should be attached to each head. When the machine has no nozzle station or uses a
head not designed for auto nozzle change. Check that the correct nozzle is attached to each head by referring to the
displayed list.
3. [Feed Bulk] button
Cannot be used with this machine.
4. [Check Nozzles] button
Checks the nozzle tip condition with the vision camera. If an error occurs with this check, clean the nozzle.
c
4
Set the operation speed.
The currently set operation speed is displayed in the "Speed" box. Press the UP arrow button to change
te operation speed.
Set the operation speed.
Setting the operation speed
24303-L4-20
5
Start operation.
1. Release the emergency stop button, and press the [READY] button on the operation panel.
2. Check that the surroundings are safe, and then press the [START] button on the operation panel.
3. When the entrance sensor detects a board, the conveyor belt will start rotation. The board will be
transferred to the work position, and component mounting will start.
w
WARNING