Device Name Chip Mounter Block Name Page No. Unit Name Revision Model Item GXH-1 Chapter 15 Others 2. Attachment of Operation Monitor 2.1 Setting of Operation Monitor Set the dip switches located on the back of the opera…

100%1 / 325
0406-001 15-B
Device
Name
Chip Mounter
Block Name
Page No.
Unit Name
Revision
Model ItemGXH-1
Chapter 15 Others
2. Attachment of Operation Monitor
2.1 Setting of Operation Monitor
Set the dip switches located on the back of the operation monitor. (Fig. O1)
2.2 Fix the monitor to the frame.
Fix the operation monitor to the frame with four fixtures.
2.3 Connect the connector to the operation board.
Insert the connector to the UB13 board for operations (Fig. O3) and attach the cover with
seven bolts as shown in Fig. O4.
Do not make a mistake in connector insertion (R and L Sides).
0406-001
15-1
Fig. O1
Fixtures
Fixture
Fig. O2
Fig. O4
UB13
Fig. O3
Device
Name
Chip Mounter
Block Name
Page No.
Unit Name
Revision
Model ItemGXH-1
Chapter 15 Others
2. Attachment of Operation Monitor
2.4 Attachment of Operation Monitor to Main Machine
Attach the operation monitor to the main machine. (Fig. O5)
Fix the monitor, keeping both right and left sides of the monitor horizontal, and adjust the
height so that the upper side of the monitor can be aligned with the ceiling of the machine.
(Fig. O6)
2.5 Cable Connection
Connect the cables running from the main machine with the boards (UB13) for the monitor
and the operation.
Do not make a mistake in connector insertion (R and L Sides).
2.6 Attachment of Keyboard
After the USB connections (Fig. O7), attach the keyboard. (Fig. O8)
Fig. O6
Fig. O5 Back of Monitor
Anchor Bolts
Fig. O7 USB Connections (2 Places)
Fig. O8
0406-001