Flowchart "Switching ON the SIPLACE Line"
Test set-up
Reset tracks
No
Line computer tasks
Load cluster data
Make settings on the machine
Set-up generator appears
Check the set-up
(insert feeder modules)
Switch on
Nozzle check
Change nozzle
configuration, if necessary
Wait for PCB
Introduce PCB
Tra ck
errors
Ye s
Abort
processing PCB
Ye s
PCB onto output conveyor
No
Station computer
Bold :
Italic :
To be carried out
by the operator
Carried out or
signaled by the
station
Confirm the
set-up generator
Fiducials
OK?
Siemens AG 2001 All rights reserved Subject to change without prior notice
Order no.: 00192419-02 Siemens Aktiengesellschaft
To be ordered from:
Siemens PLS AG
PL EA 1 V GC DOK
Printed in the Federal Republic of Germany