1 Installation 1-3 How to Hoist the Machine Be sure to use the bolts wh en hoisting the machine. ■ Recommended Bolt Size ● Type 1 (M20 x P2.5) ● Type 2 (M20 x P2.5) [Unit = mm] M x P D d d1 L2 L3 S T L R H B C Type1 Type…

1 Installation
1-2
Installation of Machine
Environmental Requirements
Install the machine at the place where the below conditions are met.
Do not do tasks, such as moving the machine or connecting the machine with the main switch ON to
prevent electric shock.
Warning
■ Ambient Temperature: Accuracy assurance 23 +/-2 degrees centigrade
Operation assurance 5 to 40 degrees centigrade
(The average over a period of 24 hours does not exceed 35 degrees C.)
■ Relative Humidity: 45 to 60 percent, non-condensing
■ Atmosphere: Dust and corrosive gas free
■ Floor: Floor must be flat and sturdy enough for freedom from vibration during
operation.
■ Power Requirements: 200 VAC +/- 10%, three phase, 50/60 Hz
* 208/220/230/240/380/400/415/440 VAC with optional power
transformer
Power consumption: 2 kW
Capacity: 5 kVA
Leakage current: 100mA or less
* Power and ground the machine independently of other machines which may be a
noise source, such as a compressor, welding machine, or reflow soldering machine
with magnetic contacts.

1 Installation
1-3
How to Hoist the Machine
Be sure to use the bolts when hoisting the machine.
■ Recommended Bolt Size
● Type 1 (M20 x P2.5)
● Type 2 (M20 x P2.5)
[Unit = mm]
M x P D d d1 L2 L3 S T L R H B C
Type1 Type2
Type1 Type2
20x 2.5
25 48 62 20 28 37 32 16 90 98 2 12 17 19.8

1 Installation
1-4
■ How to Hoist
Use the bolts, wires, and the arm as the following diagram shows.
Bolt
Arm
Front View
Arm
Side View
NOTE: Be sure to use the arm to prevent the wire from touching the machine.