00193922-01 - 第148页

4 Setting up and commissioning User Manual SIPLACE HF Series 4.3 Delivery configuration and transport Sof tware Version SR.505.xx 05/2004 US E dition 148 4.3 Delivery configur ation and transport 4.3.1 T ransport p ackag…

100%1 / 358
User Manual SIPLACE HF Series 4 Setting up and commissioning
Software Version SR.505.xx 05/2004 US Edition 4.2 Dimensions of the placement systems
147
4.2.2.2 Dual conveyor
4
Fig. 4.2 - 6 Distance between the right-hand side of the PCB conveyor and the machine center in millimeters
(dual conveyor)
4
M Machine center
T Direction of PCB transport
4 Setting up and commissioning User Manual SIPLACE HF Series
4.3 Delivery configuration and transport Software Version SR.505.xx 05/2004 US Edition
148
4.3 Delivery configuration and transport
4.3.1 Transport packaging
The placement machine is supplied in a wooden crate mounted on a stable wooden pallet.
4.3.1.1 Dimensions of the transport packaging
The dimension of the wooden transport crate are as follows:
Length 2404 mm
Width 2790 mm
Height 1600 mm 4
4
Fig. 4.3 - 1 Transport crate - dimension in millimeters
(A) Fork-lift attachment points
4.3.1.2 Weight of the placement machine prepared for dispatch
The weight of the placement machine prepared for dispatch, including packaging, is 4287 kg for
the HF machine and 4337 kg for the HF/3 machine.
4.3.2 Configuration when delivered
The placement machine is configured as follows when delivered:
The extension kit on the PCB input side (point 1 in Fig. 4.2 - 3
) is removed from the basic ma-
chine.
All electrical cables to the basic machine are disconnected.
Each track on the single or dual conveyor is set to a width of 136 mm. This width setting will
User Manual SIPLACE HF Series 4 Setting up and commissioning
Software Version SR.505.xx 05/2004 US Edition 4.3 Delivery configuration and transport
149
be important when fine-tuning the machine.
The electrical plug-in connections on the conveyor motor and the conveyor light barrier for the
left-hand track are then easily accessible on the dual conveyor.
The input conveyors of the single and dual conveyor are dismantled. The electrical cables to
the conveyor motors and light barriers are disconnected.
Both keyboards (point 4 in Fig. 4.2 - 3
) are folded down vertically.
The main fault indicator is dismantled (point 6 in Fig. 4.2 - 3
).
All the gantry axes are fixed with shipping braces.
4.3.3 Transporting the placement machine in the crate
4.3.3.1 Services
As a service, SIEMENS L&A can fully integrate the SIPLACE HF placement machine into your
production line. With our extensive expertise and by using the right tools and equipment, we can
ensure that the installation process runs smoothly and efficiently. However, this will require you to
clarify the infrastructure aspects in advance and make any necessary changes at your production
facility.
Please note that the safest way to transport the placement machine is always in the transport crate
- or at the very least on the pallet. This will prevent serious damage to the machine caused by the
feet colliding with obstacles, for example.
4.3.3.2 Safety instructions
WARNING
The applicable accident prevention regulations concerning the transportation of heavy goods
must be followed.
There is a risk that the machine will tip over if you do not use the fork-lift specified in section
4.3.3.3
to transport the placement machine.
In particular, you should wear safety boots to minimize the risk of crushing your feet.
4.3.3.3 Means of transport
Use a fork-lift truck with the following specification to carry the machine in its crate:
Fork length: min. 1800 mm
Carrying power: min. 6000 kg
Clear width between forks: min. 350 mm 4