Edison Printer User Manual (Part Number 1023838) I NSTALLATION AND I NITIA L S T A RT - U P Rev. A 65 Copyright © 2017 ITW EAE All rights reserved. No part of the contents of this manual may be reproduced, copi ed or tra…

100%1 / 172
INSTALLATION AND INITIAL START-UP Edison Printer User Manual (Part Number 1023838)
64 Rev. A
Copyright © 2017 ITW EAE
All rights reserved. No part of the contents of this manual may be reproduced, copied or transmitted in any form or by any
means including graphic, electronic, or mechanical methods or photocopying, recording, or information storage and
retrieval systems without the written permission of ITW EAE, unless for purchaser's personal use.
3.7.7. Secure the Power Cable
Unplug the power cable and place it inside the printer between the computer and the pneumatics
panel.
3.7.8. Hood Block Installation
Close the hood and, while doing so, place two foam blocks (one on each side) between the hood
and the side covers.
3.7.9. Pack and Secure the Monitor/ Monitor Arm
1. Unplug and remove the monitor from the monitor arm.
2. Screw the monitor mounting hardware into the back of the monitor, then pack the monitor in
a box for safe keeping.
3. Flip up the keyboard tray and apply bubble wrap to the tray and mounting bracket. Position
the arm against the side of the printer.
3.7.10. Crate the Printer
Attention
ITW EAE recommends using extended forklift blades of 60 in
to 72 in (152.4cm to 182.8cm) in length to ensure proper
weight distribution of the printer.
Forklift blades must have a total width/span of 36 in
(91.44cm).
Ensure forklift blades are placed within the area designated
by the left and right forklift blade labels, located on the sides
of the printer.
Forklift must be capable of lifting 3000 lbs. (1360.7 kg)
Attention
Install the shipping isolator mounting hardware in the same
holes used for the leveling pads.
Edison Printer User Manual (Part Number 1023838) INSTALLATION AND INITIAL START-UP
Rev. A 65
Copyright © 2017 ITW EAE
All rights reserved. No part of the contents of this manual may be reproduced, copied or transmitted in any form or by any
means including graphic, electronic, or mechanical methods or photocopying, recording, or information storage and
retrieval systems without the written permission of ITW EAE, unless for purchaser's personal use.
1. Position forklift blades under the printer base within the area designated by the left and right
forklift blade labels and confirm that the forklift blades do not pinch any loose pneumatic or
electrical lines and fully extend across the printer base.
2. Lift the printer high enough to remove the leveling pads and install the isolators to the bottom
of the printer.
3. Using a 30mm open end wrench, loosen the top hex nut of the leveling pad, then on the very
bottom of the leveling pad use a 10mm socket to 3/8 in socket (METRIC?), remove the
leveling pads from each corner of the printer.
4. Install the isolators on the bottom of the printer, using a 30mm socket.
5. Install the foam plugs.
6. Orient the skid so the isolator pads will sit on top of the skid feet when the printer is
completely lowered onto the skid.
7. Slowly lower the printer down to the skid, centering the isolator pads over the center of the
skid feet.
8. Secure the isolators to the platform using a ¾ in. socket on the lag bolt mounting hardware.
9. Slide the two support timbers under the printer along the inside edges of the isolators. Secure
the timbers to the platform using the appropriate mounting hardware.
10. Install the front, rear, and two side panels.
11. Install the crate cover.
PROCESS PROGRAM CREATION Edison Printer User Manual
66 Rev. A
Copyright © 2017 ITW EAE
All rights reserved. No part of the contents of this manual may be reproduced, copied or transmitted in any form or by any
means including graphic, electronic, or mechanical methods or photocopying, recording, or information storage and
retrieval systems without the written permission of ITW EAE, unless for purchaser's personal use.
4. Process Program Creation
Use the Intueri Process Program page to develop new process programs.
Process program development is done through the Intueri Process Program page. This section
describes that page, and provides instructions for creating and saving process programs.
4.1. Access the Process Program Page
Access the process program page to create a new
process program by navigating to File > New >
Process Program
(Figure 40).
Alternately, select Ctrl + N to create a new
process program.
Hover over a parameter field a brief description for
any given parameter. Click the field to activate it
for the purpose of inputting a value.
Figure 40. Access the Process Program Screen.