2.15 Automatic Recovery (Priority of Component) Function When this function is used, the machine does not stop immediately after it has detected a component shortage, etc. When the machine has detected a component shorta…

100%1 / 469
2.14 Placement Coordinates Teaching Function
P.C.B. Origin Offset Teaching
When the placement coordinates in the pattern program are shifted
overall in the X and Y directions, such overall deviations can be cor-
rected by changing the P.C.B. origin offsets X and Y in the operation
data.
This function can be used to calculate the amount of deviations semi-
automatically with the P.E.C. recognition camera and reflect the re-
sults as P.C.B. origin offsets X and Y for correction of the overall
deviations in the X and Y directions.
Placement Coordinates Teaching
By capturing the image of P.C.B. patterns in the recognition window
with the P.E.C. recognition camera, it can be checked if wrong pa-
rameters are specified individually as placement coordinates in the
pattern program.
When a mistake is found, this function can be used to correct the
pattern program data, using the manual alignment function (match-
ing operation of displayed component outlines and P.C.B. patterns
with the pointing device).
Table 2B14
Step Reference
1. P.C.B. Origin Offset Teaching "5.3 "PCB Origin Offset Teach" Tab" in "Section 5"
2. Placement Coordinates Teaching "5.4 "Place Pos Teach" Tab" in "Section 5"
2.14 Placement Coordinates Teaching Function
0308-002 2-25 AHB01ESPP
2.15 Automatic Recovery (Priority of Component)
Function
When this function is used, the machine does not stop immediately
after it has detected a component shortage, etc.
When the machine has detected a component shortage, etc., a mes-
sage is issued as machine information, prompting the operator to re-
plenish components.
The machine continues to place the components other than the miss-
ing ones (component-shortage detected ones). After it has placed all
components (excluding the missing ones), it stops running without dis-
charging the P.C.B.
When component shortage errors, etc., are detected in different feed-
ers at a short interval, the loss time can be reduced because the com-
ponents in short can be replenished collectively.
Table 2B15
Step Reference
1. Setting of Operation Mode "3.3 "Opn. Mode" Tab" in "Section 5"
2.15 Automatic Recovery (Priority of Component) Function
0206-001 2-26 AHB01ESPP
Section 3
Program Change Operation
This section describes the procedure of program change
operation for the model to be produced for the first time.
0308-002 3-A AHB01ESPP