00193802-01 - 第116页
4 Setting up t he placement system User Manual S IPLACE CF 4.3 Adapting the com ponent trolley to another PCB transport height Software version S R.101.xx 06/2003 US Edition 116

User Manual SIPLACE CF 4 Setting up the placement system
Software version SR.101.xx 06/2003 US Edition 4.3 Adapting the component trolley to another PCB transport height
115
(1) Clamping screws, 4 per side
(2) Holes in the cross-beam for adjusting the table height to 830, 900, 930 and 950 mm
Æ Insert the two Allen keys (8 mm) into the correct holes for the current PCB transport height (see
Fig. 4.3 - 1
).
Æ Loosen the four clamping screws on both sides of the component trolley (see point 1 in Fig.
4.3 - 1
).
Æ Ask two people to help you raise and lower the table bed: they should hold the table bed while
you remove the two Allen keys.
Æ Raise or lower the table bed to the desired PCB transport height.
Æ Push the two Allen keys (8 mm) into the hole for the new transport height.
Æ Turn the Allen keys so that the cross-beam (item 2 in Fig. 4.3 - 1) is seated on the edge of the
keys. You can then fix the cross-beam in place and easily pull out the Allen keys.
Æ Fix the cross-beam on both sides with the four clamping screws (item 1 in Fig. 4.3 - 1).
Æ Now turn the Allen keys slightly and remove.
4 Setting up the placement system User Manual SIPLACE CF
4.3 Adapting the component trolley to another PCB transport height Software version SR.101.xx 06/2003 US Edition
116

User Manual SIPLACE CF 5 Operator, Line engineer, Service engineer
Software version SR.101.xx 06/2003 US Edition 5.1 Personnel profile
117
5 Operator, Line engineer, Service engi-
neer
This chapter contains a number of subjects that are intended to help you during your daily work
on a SIPLACE line.
For example, you are provided with preventative measures that you can take to minimize the
down time on the machine to obtain the highest possible level of efficiency for the SIPLACE line
during production.
In addition, the tasks of the operator and of the line engineer are described in an operator and line
engineer profile, respectively, in this chapter.
5.1 Personnel profile
5.1.1 Operator
The operating personnel are to be assigned the following tasks:
– Checking the assignment of components to the feeders
→ In addition, a set-up check is to be carried out several times a day, preferably at the start of
a shift, to make sure that the correct components are set up.
– Supplying the feeder with sufficient components
– Promptly refilling the components and splicing the tapes
– Checking to make sure that the components are in their correct pick-up positions (see Fig. 5.7
- 2)
– Checking the flow of material to the PCBs on the input and output conveyor
– Checking the set-up quality
– Random sampling of the PCBs before they enter the soldering furnace.
– Observing the ESD regulations
– Preventing errors (see Section 5.7
, page 127)
– Observing the fault displays and messages at the station and passing the information on to the
line engineer if necessary
– Carrying out the preventive maintenance work specified in the Preventive Maintenance Man-
ual