SW 703 Option WPC - WP C fill completed. : 116 WPC fill complete d. The set up is now completed 1. The st atus message s shows that th e machine is ready to start production and is waiting for a PCB.

100%1 / 198
SW 703 Option WPC - WPC fill completed. :
115
WPC fill completed.
1. Fill Quantity.
2. Level of the tray that has been filled (here the lowest
tray).
3. Select ‘Refill position’ – ‘Stop refilling position’.
The WPC will now move back to the operational position.
4. Click on the return to the Main Menu icon.
SW 703 Option WPC - WPC fill completed. :
116
WPC fill completed.
The set up is now completed
1. The status messages shows that the machine is
ready to start production and is waiting for a PCB.
SW 703 Option WPC - WPC verification :
117
WPC verification
The WPC setup verification can be carried out separately
for each location.
1. Check and see if the setup is displayed as online
setup in Setup Center.
2. Scan the control barcode Table verification of the
location to be verified. Check if you at the right track.
3. Scan all configured barcodes of the packaging unit.
Repeat step 4 until all the necessary tracks for the
current job are verified.
NOTICE! Depending on the configuration of
Setup Center further steps can be necessary during
online setup verification. Therefore always watch the
display of the barcode reader.