Refilling Component Reels - Refill a track :
127
Refilling Component Reels
Continuously check the component reels to see if they
are running out – if there is around 1m of tape remaining
then it is time to splice a new reel!
Obtain the new reel of components from the storage
location.
1. Scan the control barcode Refill of the location to be
verified.
2. Scan the Track barcode of the packaging unit be
refilled.
3. Scan all configured barcodes of the packaging unit.
NOTICE! Depending on the configuration of
Setup Center further steps can be necessary during refill.
Therefore always watch the display of the barcode
reader.
e.g. scanning of user or reordering a packaging unit.

Refilling Component Reels - Splicing - Required Tools and Materials :
128
Splicing - Required Tools and Materials
These tools and materials are required for tape splicing.
1. Adhesive tape (small)
2. Tweezers
3. Scissors
4. Splicing rivets
5. Splicing tool
6. Adhesive tape (large)

Refilling Component Reels - Preparation of carrier tape end :
129
Preparati on of carrier tape end
Carrier tape end:
1. Carrier tape end is protruding from the feeder
2. Cut carrier tape exactly between two pockets in the
middle of the hole, as shown in picture. All pockets
must be full to end of carrier tape
Note: Carrier tape splicing must occur with enough lead
tape length to prevent the machine to be stopped.