Preparing the Component Set Up - Steps to prepare a product to run at the line : 42 Steps to prepare a product to run at the line

100%1 / 198
Preparing the Component Set Up - What makes a Set-Up? :
41
Preparing the Compon ent Set Up
1. SMD Components
2. Feeders
3. Feeder Tables
4. Set-Up Sheet
Preparing the Component Set Up - Steps to prepare a product to run at the line :
42
Steps to prepare a product to run at the line
Preparing the Component Set Up - Printing a Set Up report :
43
Printing a Set Up report
The offline setup verification is carried out separately for
each changeover table.
1. Check and see if the setup is displayed as offline
setup in Setup Center.
2. Print the Setup Report for the setup to be verified. By
the selection window on the left border of SIPLACE
Setup Center reports can be displayed and printed
out.