SW 703 Option MTC - Loading Posit ion Of The Carrier (Tower 1) : 90 Loading P osition Of The Carrier ( Tower 1) 1. Check if all carriers are l oaded into the MTC tower 1 in correct orientation with the hinge facing outwa…

SW 703 Option MTC - Loading Of Carrier for both Towers :
89
Loading Of Carrier for both Towers
Loading of the carrier involves 4 steps, it is the same
procedure for both towers (Tower 1 is used for
illustration):
1. Push in the refilled carrier
2. Turn the latch inward to secure the carriers
3. Close the tower door
NOTICE! Always ensure that the leaf spring is
locked.

SW 703 Option MTC - Loading Position Of The Carrier (Tower 1) :
90
Loading P osition Of The Carrier ( Tower 1)
1. Check if all carriers are loaded into the MTC tower 1
in correct orientation with the hinge facing outward
WARNING! A crash may occur if the above step
is not followed.

SW 703 Option MTC - Loading Position Of The Carrier (Tower 2) :
91
Loading P osition Of The Carrier ( Tower 2)
1. Check if all carriers are loaded into the MTC tower 2
in correct orientation with the tray adaptor facing
outward
WARNING! A crash may occur if the above step