PSV7000_ Owners Manual_096-0460-001B - 第115页

■ Workspace, Head and Gantry ◘ Socket Adapters and Actuation PSV7000 Owner’s Manual 4—9 back T urning OFF Input Air Prior to turning off the input air , ensure that no job is running. CAUTION: Possible damage to programm…

100%1 / 186
Maintenance Workspace, Head and Gantry
4—8 Data I/O • 096-0640-001B
back
Workspace, Head and Gantry
The workspace includes the Socket Adapters and items on the
working surface, except not the programmers. They are covered in a
separate heading.
Socket Adapters and Actuation
Under this heading you will learn about visually inspecting, cleaning
and adjusting sockets, actuation, and air pressure for the workspace
items.
Inspecting the Socket Adapters
The condition of the Socket Adapters has great throughput conse-
quences.
Socket Life
The Run window displays the Socket Adapter
lifetime actuation count in yellow until it is
exceeded at which time it changes to red.
Socket Cleaning
WARNING: Vision hazard! Pressurized air or debris blown
into the eyes or skin could cause bodily damage. Always use
care and wear protective eye goggles when cleaning with
pressurized air.
1. Use clean, dry compressed air (at 6.2 Bars (90 PSI or less) to
remove dirt from the sockets. Actuate the sockets while blowing
them out.
2. Check the sockets for wear and replace if necessary.
Note: The socket replacement cycle depends upon the type of socket
used and the socket manufacturer.
Workspace, Head and Gantry Socket Adapters and Actuation
PSV7000 Owner’s Manual 4—9
back
Turning OFF Input Air
Prior to turning off the input air, ensure that no job is running.
CAUTION: Possible damage to programmers and devices! DO
NOT TURN AIR OR POWER OFF to the PSV7000 Machine while
a job is running.
A job must be
Finished
before turning OFF compressed air or elec-
trical power. Wait for the gantry to park before turning OFF.
1. If a job is running, Pause or Finish it.
2. On the Power Panel, rotate the valve clockwise to turn OFF the
input air; it is off when the lock rings line up. See Figure 4-1.
Figure 4-1: The input air regulator/filter on the Power Panel (on the left
side of the machine). When the lock rings on the valve line up, the air
supply to the PSV7000 Machine is OFF.
3. (Optional) Paddle lock the air shutoff valve.
Adjusting the Socket Actuator Air Pressure on the
Programmers
Socket Actuators are built into the FlashCORE programmers on
PSV7000. Socket actuation is controlled by air pressure. If Socket
Actuators are slamming up and down loudly, or devices are
bouncing, the air pressure may be too high. If the PNP head does not
properly pick or place a device in a socket because the socket is not
opening completely, the air pressure might be set too low.
Adjust the air pressure setting as follows:
1. Finish a job if one is running.
2. Navigate to the Gantry window and click the yellow label for a
programmer that is easy to see.
Maintenance Workspace, Head and Gantry
4—10 Data I/O • 096-0640-001B
back
3. At the Actuator Tab, click Actuate Socket ON and OFF to visually
verify performance for reference.
Figure 4-2: The Socket Opener Pressure Control knob with built-in
gauge on the Power Panel.
4. At the Power Panel on the left side, adjust the air pressure up or
down as desired by pulling the collar on the black knob out and
then rotating it.
5. Push the collar back in.
6. Actuate the socket as before to verify the change in action.
7. Repeat if necessary.
Note: If Socket Actuator problems persist, set the actuator speed
(refer to the next heading).
Adjusting the Socket Actuator Speed on the
Programmers
THE SOCKET ACTUATOR SPEED WAS SET AT THE FACTORY
AND SHOULD NOT NEED ADJUSTMENT. If it is determined that
adjustment is necessary, this procedure requires a Data I/O trained
technician since it requires having an access door open while the
machine power is on.
Requirements
Programmer air pressure must be correct. See previous heading.
Small flat screw driver.
To adjust the speed of the Socket Actuators:
1. Ensure that power and air are connected and ON, and a Socket
Adapter is installed on the target programmer.
2. At the Gantry window, click the label for a programmer with the
adapter installed. Probe 1 will stop over socket 1.