182049 Viking Installation Manual - 第48页
semi automatic MACHI NE PREPARAT ION MACHINE LEVELLIN G 5.22 Instal lation Manual Chapter Issue 1 Oct 02 MACHINE LEVELLING General Before operation, the machine height and level must be set. Machine Height The height of …

semi automatic
MACHINE PREPARATION
PRE-INSTALLATION CHECKS
Chapter Issue 1 Oct 02 Installation Manual 5.21
PRE-INSTALLATION CHECKS
Having removed the transit brackets and located the machine in position,
prepare to install the machine, as follows:
1. Ensure machine mains isolator is OFF.
2. Connect the pneumatic supply to the connection on the external services
panel, as detailed in the Services Required chapter of this manual.
NOTE
Do not connect the electrical supply to the machine until the electrical
services have been verified, as stated in the Electrical Services section of
the Power Up Sequence chapter of this manual.
3. Check that all circuit breakers are in the ON position.
4. Ensure that all access covers and removable panels are closed and are in
place, Safety Features chapter refers.
5. Ensure that the E Stop buttons are in the fully out position. To check this,
push the E Stop button until it latches. Twist the button clockwise to release
it.
6. Check that all the cables for the monitor and keyboard/mouse are con-
nected.

semi automatic
MACHINE PREPARATION
MACHINE LEVELLING
5.22 Installation Manual Chapter Issue 1 Oct 02
MACHINE LEVELLING
General Before operation, the machine height and level must be set.
Machine Height The height of the machine is adjustable from 820mm to 980mm which is
measured from the floor to the top of the transport belts, Machine Height figure
below refers. Ideally the machine should be set at its lowest position, with the
machine legs screwed in.
NOTE
To achieve reliable DEK SPC testing and Cp/Cpk results, the securing arrange-
ment of the four machine legs must be correct in accordance with the Mounting
Feet Arrangement diagram, (Major Relocation chapter - Unpacking section).
This arrangement increases the rigidity of securing the feet to the frame.
Figure 5-10 Machine Height
Height to Top of
Transport Belts
820mm to 980mm
View on Front of Machine
Transport Belts
Cutaway to
Show Belt

semi automatic
MACHINE PREPARATION
MACHINE LEVELLING
Chapter Issue 1 Oct 02 Installation Manual 5.23
Initial Levelling When the correct height of the machine has been achieved, the four feet should
now be adjusted for correct level.
1. Place an engineering level on the tooling base plate facing Left (L) - Right
(R) or Back (B) - Front (F).
2. By carefully adjusting each of the four feet individually, level the machine so
that in each direction, Left (L) - Right (R) and Back (B) - Front (F), 0.004" per
foot (0.32mm/metre) is achieved.
3. Lock the feet using the locknuts on the adjusters.
Figure 5-11 Machine Levelling
Isometric View Showing Levelling of Tooling Base Plate
Tooling Base Plate
Engineering Level
Adjustable Mounting Feet
(4 positions)