semi automatic MACHI NE PREPARAT ION SHOCK WATC HES 5.26 Instal lation Manual Chapter Issue 1 Oct 02

100%1 / 86
semi automatic
MACHINE PREPARATION
SHOCK WATCHES
Chapter Issue 1 Oct 02 Installation Manual 5.25
Chase Shock
Watch
If the chase shock watch has triggered, visually inspect the chase is level to the
table.
Camera Shock
Watch
If the camera shock watch has triggered, ensure that the camera is secure and
level on the camera mount (refer to Technical Reference Manual).
Machine PC Shock
Watch
If the machine PC shock watch has triggered, visually inspect the inside of the
PC and ensure that the cards are seated correctly.
Machine Controller
Shock Watch
If the machine controller shock watch has triggered, visually inspect the
machine controller to ensure that the cards are seated correctly.
Shock Watch
Replacement
On completion of corrective action, replace any triggered shock watches.
NOTE
The machine should be fitted with four untriggered shock watches at all times.
semi automatic
MACHINE PREPARATION
SHOCK WATCHES
5.26 Installation Manual Chapter Issue 1 Oct 02
semi automatic
POWER UP SEQUENCE
GENERAL
Chapter Issue 1 Oct 02 Installation Manual 6.1
CHAPTER 6 POWER UP SEQUENCE
GENERAL
Before the machine is powered up, a final check is required to ensure proper
installation. When fully satisfied that all instructions and preparations have been
carried out as detailed in the Machine Preparation chapter, proceed with the
power up checks detailed in this chapter.
Electrical Services Check the following electrical services are available:
The machine transformer must be tapped to the nearest selectable voltage
within the following limits:
100V, 110V and 120V ±5%
200V, 210V, 220V, 230V and 240V ±2.5%
CAUTION
VOLTAGE CONFIGURATION.
The factory set voltage configuration may
differ from the customers own supply.
- Ensure correct transformer configuration is used
- Ensure that the machine serial plate is annotated correctly
- Ensure filtration unit (if fitted) is voltage compatible
NOTE
For information on the filtration unit, Machine Relocation section of the Machine
Preparation chapter of this manual refers. Refer to Technical Reference
Manual, Power Supply and Distribution chapter for more detailed information.
Detail Voltage
Measured Customer/Factory electrical supply
Detail Accept Reject
Check dispatch documentation and serial number plate on rear
of machine matches supply